Air conditioning commissioning and handover: a checklist for the homeowner
What an installer tests, shows and hands over when a new air conditioner is finished, with a checklist of the documents and details to collect on the day.
Last updated
Commissioning is the testing and setting up an installer does once the units are fitted, before the system is yours to use. Handover is the end of the job: you see the system run, you are shown the controls and you are given the documents. Go through the checklist on this page with your installer before they leave.
How to use this guide
Step 1: Know what is tested
What an installer checks before a new system is handed over.
Go to What is testedStep 2: Fill in the checklist
Go through it with the installer on the day, room by room.
Go to the recordStep 3: File the papers
What to keep in one place, and why the next technician will ask for it.
Go to What to keep
What is commissioning, and what does the installer check?
A home split system or ducted system comes as a matched set from one maker, and the maker's installation manual sets out how it is commissioned. The detail differs from model to model. The ground covered is much the same. When we commission a system we:
- make sure both units are level and firmly fixed, and that the outdoor unit has clear air around it
- see that the pipework is supported and insulated along its whole length, with the outdoor run protected from the sun
- pressure test the pipework for leaks before the system is charged and started
- confirm the amount of refrigerant suits the length of pipe, and mark the unit if any was added
- prove that water drains freely from the indoor unit to the end of the drain, without sitting anywhere along the way
- run the system in every mode and at every fan speed, and watch for fault lights, vibration and noise
- make sure the controller reads and responds as it should, and set up any app or wifi connection
- on a ducted system, balance the airflow to each outlet and go over the zones and the filters
Testing is part of the installation and not an extra. The Building and Plumbing Commission's practice note for split systems (opens in a new tab) says that once the installation is complete, tests must be carried out for leaks in the refrigerant piping and for the correct operation of the drain. Its commissioning checklist ends with instructing the customer in how to operate the equipment.
These are the installer's tests. They involve refrigerant under pressure and live electrical parts, so none of them is a job for an owner. Your part is to see the system running, to be shown how it works and to collect the record.
What should the installer show you?
A system you cannot work is not finished. Before we leave we go through it with you, and any installer should do the same:
- how to choose each mode: cooling, heating, dry, fan and auto
- how to set the temperature, the fan speed and the direction of the air
- how the timer and any other programmed settings work
- how to use the remote or the phone app, and how to connect the app again if your wifi changes
- on a ducted system, how to turn each zone on and off
- how to take the filters out and clean them, and how often to do it
- what to expect on a very hot or a very cold day, including how long a room takes to come to temperature
- what servicing the system needs, and when the first service is due
- who to call if something is not right
Ask to do each thing yourself while the installer watches. It is the quickest way to find the step you did not follow. The manual for your model has the detail, so keep it where you can find it.
What documents should you receive?
In Victoria, installing an air conditioner is plumbing work (opens in a new tab) and electrical work, and each has its own document. An Energy Safe Victoria fact sheet (opens in a new tab) says the customer must be given both. The rest of the list is what a careful installer hands over with them.
| Document | What it is | When you get it |
|---|---|---|
| Plumbing compliance certificate | The record of the plumbing work, for plumbing work with a total value of $750 or more. The total counts materials, anything installed and labour. It should describe the work and list the model and serial numbers. | The licensed plumber gives it to you, and lodges it with the Building and Plumbing Commission, within five days of finishing. |
| Certificate of Electrical Safety | The record of the electrical work. One is required for all electrical installation work. | Air conditioning work is non-prescribed electrical work, and for that you get a copy within 30 days. Work on the main switchboard is prescribed work, which an independent inspector looks at first. |
| Commissioning record | The tests that were done and their results, with the type of refrigerant and the amount in the system. | At handover. The national refrigerant handling code (opens in a new tab) lists commissioning data among the documents an installer must provide with a completed system. |
| Manuals | The maker's operating manual for the system and its controller. | At handover. |
| Warranty papers | The maker's warranty on the equipment and the installer's terms for the installation work, in writing. | At handover, filled in. |
| Quote and invoice | What was agreed and what was supplied, with the equipment named by brand and model number. | With the bill. |
| Sizing notes | How the capacity was worked out for your rooms. | On request. They are useful if a room is extended later or the system is replaced. |
The plumbing rule is in the Building Act 1993 (opens in a new tab) and explained by the Building and Plumbing Commission (opens in a new tab). The electrical rule is set out by Energy Safe Victoria (opens in a new tab).
A warranty sits on top of your rights under the Australian Consumer Law. The ACCC (opens in a new tab) says warranties are extra promises a business may make on top of the consumer guarantees, and nothing a business says or does can take those consumer guarantees away. See the guide to warranties, workmanship and consumer guarantees.
What should you look at before the installer leaves?
You do not need to test anything. Walk around the job with the installer and look, without touching the equipment.
| Where to look | What you should see |
|---|---|
| Indoor unit | Level and firm on the wall, with no gaps or marks left around it. |
| Outdoor unit | Level, fixed to its slab or bracket, clear of plants and stored things, and easy to reach for servicing. |
| Pipes outside | Insulated the whole way and covered or otherwise protected from the sun, with the cover fixed and its joins closed. |
| Where the pipes go through the wall | Sealed, so that water, draughts and insects stay out. |
| The drain | Ending where you agreed, where you can see it, and not across a path or against the foot of the wall. Once the system has been cooling for a while, water drips from it. On a dry day there may be very little. |
| The isolating switch | A switch beside the outdoor unit that turns its power off. Know where it is. |
| The switchboard | A label on the air conditioner's circuit breaker, so anyone can tell which one it is. |
| Making good | Holes patched, old brackets and pipe gone if that was agreed, and the rubbish taken away. |
These are the things the plumbing regulator's own auditors look at. The Building and Plumbing Commission's audit checklist for split systems (opens in a new tab) asks, among other things, whether the indoor unit is level, whether the outdoor unit is mounted and supported correctly and can be reached for servicing, whether wall penetrations are finished and weathered, and whether the drain ends correctly.
What if something is not finished?
A job can be handed over with something still to come. The Certificate of Electrical Safety can follow within 30 days, and a part or a finish may be on order. That is fine as long as it is written down.
- Write down each thing that is outstanding, who will do it and by when.
- Ask the installer to confirm the list in writing, in an email or on the invoice.
- Add the date each item is done, and keep the list with the other papers.
If a document does not arrive, ask the installer first. For the electrical one, Energy Safe Victoria (opens in a new tab) will search for a copy at no fee for an owner, an occupant or the customer who cannot reach the electrician, and asks customers to report a contractor who refuses to provide one.
What should you keep, and why?
Put everything from handover in one folder, on paper or on your phone, and add to it each time the system is serviced. It is the first thing a technician asks for, and it answers most of our questions before we arrive.
- The model and serial numbers of the indoor and outdoor units, and the date they were installed. A warranty claim and a parts order both start with them.
- Both regulated documents and the commissioning record, which shows the type of refrigerant and how much is in the system.
- The warranty papers, with the date each warranty ends.
- Photos taken on the day of each unit and of the route the pipes and the drain take. They show where things run once the covers are on.
- Each service report after that: the date, who came and what they did.
Ask at handover when the first service is due and put it in your calendar. The air conditioner servicing page says what a service covers, and the guide to planning a service covers how often. If you sell the house, leave the folder for the buyer.
Air conditioner handover checklist
Fill this in with the installer before they leave. The model and serial numbers are on a label on each unit, and the installer can read them out. Leave a line blank if it does not apply to your system.
Other questions about commissioning
Who can commission an air conditioner?
Someone with a refrigerant handling licence. The Australian Refrigeration Council (opens in a new tab) says the licence is needed to install, commission, service and decommission equipment that holds a scheduled refrigerant. In Victoria commissioning is also part of refrigerated air-conditioning work (opens in a new tab), which is a class of plumbing work. You can check a technician's licence at Look for the tick (opens in a new tab).
How do I know the right amount of refrigerant is in the system?
You cannot test it yourself, and you should not need to. The commissioning record states the type of refrigerant and the amount, and where the installer added some for a long pipe run, the new total is marked on the unit. The guide to standard and non-standard installation explains how the length of the pipes changes the amount.
Does a ducted system need more at handover than a split system?
Yes. The air has to be shared out between the rooms, so we balance the airflow at each outlet, set up the zones and show you where the return air filter is and how to clean it. Ask to be shown each zone working.
What if the system does not seem right in the first weeks?
Call the installer, and write down what the system is doing before you ring. The guide to an air conditioner that is not cooling or heating lists what to check and record.
Sources (15)
- Building and Plumbing Commission: practice note MS 07, split system air conditioning, 29 August 2024 (opens in a new tab) Checked on 19 November 2026.
- Building and Plumbing Commission: audit checklist 97.2, split system air conditioning (opens in a new tab) Checked on 19 November 2026.
- Australia and New Zealand refrigerant handling code of practice, part 2, 2025 edition (opens in a new tab) Checked on 19 November 2026.
- Energy Safe Victoria: air conditioning systems fact sheet (opens in a new tab) Checked on 19 November 2026.
- Energy Safe Victoria: Certificate of Electrical Safety (opens in a new tab) Checked on 17 November 2026.
- Energy Safe Victoria: Certificates of Electrical Safety for the community, reviewed 17 September 2026 (opens in a new tab) Checked on 19 November 2026.
- Energy Safe Victoria: EIS 007, common electrical defects in split system installations, reviewed 13 May 2024 (opens in a new tab) Checked on 19 November 2026.
- Building Act 1993 (Victoria), version of 13 November 2026 (opens in a new tab) Checked on 17 November 2026.
- Building and Plumbing Commission: compliance certificates (opens in a new tab) Checked on 17 November 2026.
- Plumbing Regulations 2018 (Victoria), version 010 (opens in a new tab) Checked on 17 November 2026.
- Australian Refrigeration Council: frequently asked questions (opens in a new tab) Checked on 17 November 2026.
- Australian Refrigeration Council: Look for the tick (opens in a new tab) Checked on 17 November 2026.
- ACCC: misleading consumers about their rights under the consumer guarantees (opens in a new tab) Checked on 17 November 2026.
- AIRAH: residential air conditioning best practice guide (Victoria), second edition 2026 (opens in a new tab) Checked on 19 November 2026.
- ABL Refrigeration: air conditioning services (opens in a new tab) ABL's own page. Checked on 19 November 2026.
Related pages
- Split system installation in Bairnsdale and East Gippsland
What ABL installs, and how to ask for a quote.
- How to prepare your home for air conditioning installation day
What to have ready before the installers arrive.
- Electrical requirements in an air conditioning quote
What the electrical part of the job involves and who signs it off.
Having a new system installed?
Call ABL or send an enquiry to ask about an installation and the paperwork that comes with it.
Filled in the record? Copy or print it first: it is not sent with a call or an enquiry.