Replacing commercial air conditioning while the business stays open

How to stage a commercial air conditioning replacement around a working business: shutdown windows, temporary arrangements, who does what, and a plan to fill in.

Last updated

A commercial air conditioning system can be replaced while the business keeps trading. The work is split into stages, each stage gets an agreed shutdown window, the areas that lose heating or cooling get a temporary arrangement, and each stage is tested and handed over before the next one starts. Fill in the staging plan in this guide before you ask for quotes, so every contractor prices the same job.

How to use this guide

  1. Step 1: Map

    List each area, what happens there and how long it can go without air conditioning.

    Go to Map the areas
  2. Step 2: Plan

    Fill in the staging plan: the windows, the temporary arrangements and who does what.

    Go to the record
  3. Step 3: Send

    Paste the plan into your enquiry, or have it open when you call.

    Call (03) 5153 2650

Can commercial air conditioning be replaced while the business stays open?

In most buildings, yes. How much of the building is off at once, and for how long, comes down to a handful of things about the site. We look at each of them on a site visit before we quote.

What decides how a replacement can be staged
What we look atWhy it matters to staging
How many separate systems there areA building served by several independent systems can be changed over one system at a time while the others keep running. A building on one central system loses all of its air conditioning during the changeover, so the window has to be longer or better timed.
Where the plant sitsUnits on a roof or a plant platform usually need a crane or a hoist, which fixes the day and the hour. Indoor units above desks, counters or stock mean that area is cleared while we work overhead.
What the new system can reuseDucts, drains, cable routes and platforms that are sound and suit the new equipment shorten each stage. Anything that has to be renewed adds time while the area is off.
The electrical supplyNew equipment can need a different supply from the old. A licensed electrician does that work, usually before the first changeover so that no stage waits on it.
When the building is in useTrading hours, closed days and quiet seasons decide which windows exist. A seven day business has fewer than an office that shuts at weekends.
The time of yearA changeover in mild weather is easier on everyone inside. Around Bairnsdale that means autumn and spring.

As a guide to the changeover itself, we allow four to six hours to install a standard split system in a home and one to three days for a ducted system. A commercial job takes longer where access is harder, the plant is bigger, or the work has to stop and start around trading.

Map the areas that must stay occupied

Start with a list of every area the system serves. For each one, write down what happens there, when it is in use, and the longest it could go without heating or cooling before the business is affected. That last answer sets the shutdown windows.

Areas to map, and what to write down for each
AreaWhy it mattersWrite down
Customer areasA shop floor, dining room, waiting room or reception. Comfort here affects trade, and customers cannot be asked to put up with work overhead.Trading hours, the quietest day and time, and whether the area can close for a day.
Staff work areasPeople working at a desk or a counter feel a hot or cold room quickly, and an employer has duties to them.Who works there, their hours, and where they could work instead.
Rooms that must stay coolA room that holds computer or phone equipment, or stock that spoils in the heat, can need cooling around the clock whether or not anyone is in it.What is in the room and the temperature it needs. Plan its changeover separately, with its own temporary cooling.
Back of houseStorerooms, corridors and rooms used for part of the week can go without for longest, which makes them a good place to start.The days and hours they are empty.
Neighbouring tenanciesWork on a shared roof, a shared plant area or a common wall affects people who are not your staff.Who they are, and who will tell them.

For staff areas there is official guidance to plan against. WorkSafe Victoria's compliance code for workplace facilities and the working environment (opens in a new tab) says a workplace where people do seated or desk work should be kept at between 20°C and 24°C, depending on the time of year and the clothing worn, and that employers should consult their employees about comfortable working temperatures. Give a temporary arrangement to any area that would sit outside that range for more than a short window.

Agree the shutdown windows

A shutdown window is an agreed period when the air conditioning in one area is off and the people working on it have the space. A good window is long enough to finish and test the stage, falls when the area is empty or quiet, and has a fallback date in case the weather or a delivery lets it down.

Shutdown windows and what each one suits
WindowSuitsWatch for
Before opening or after closingA single split system, or one indoor unit at a time.Short windows suit small stages only, and after-hours work costs more.
A weekend or a closed dayA ducted system, or several small systems in one visit.Access, alarms and lifts on a day the building is shut. A seven day business may have to close one area.
A planned closureA whole-building changeover, or the stage with the longest outage.Other trades want the same dates, so book early. The guide to planning shutdown work and staged maintenance covers using a closure.
During trading, one area at a timeA building with several independent systems, where each area can be closed off or do without for a few hours.Work overhead, dust and noise next to people. The area under the work is closed while we are in it.

Pick the season as well as the day. The Bureau of Meteorology's records for Bairnsdale Airport (opens in a new tab) put the average daily maximum at 20.8°C in April, 17.7°C in May, 18.0°C in September and 20.0°C in October, against 25.9°C in January and 14.7°C in July. On average about one day in April and one in October reaches 30°C, against about six in January. A changeover booked for autumn or spring is the least likely to leave an area too hot or too cold.

A window also has to be safe to work in. Settle these before a date is fixed:

  • which circuits are switched off and for how long, so nothing else in the building loses power by surprise
  • where a crane or a truck will stand, and which entrance, car park or footpath is closed while it lifts
  • which rooms and corridors are emptied for the work, and which exits stay clear for everyone else
  • when the noisy and dusty work happens, such as drilling and cutting
  • who opens up, who holds the keys and alarm codes, and who is phoned if something unexpected turns up
  • what happens if the stage cannot be finished in the window: the old system stays in service, or the temporary arrangement carries on

If a crane or a truck has to stand on the street or the footpath, the work may need consent from the road authority. East Gippsland Shire Council has an application for works within the road reserve (opens in a new tab). Ask whoever arranges the lift to confirm what applies, and allow time for it when the date is set.

Have the asbestos register ready too. WorkSafe Victoria says the person who manages or controls a workplace must identify the asbestos in it so far as is reasonably practicable, and that this person or the employer must keep an up to date asbestos register (opens in a new tab) and make it available to contractors who may come across asbestos. In a leased building the structure is usually under the owner's control, so a tenant without a register asks the landlord for one. New pipe and cable routes mean holes through walls, ceilings and roofs, so we ask for the register before the site visit.

Choose a staging order that avoids mismatched systems

The order of the stages matters as much as their timing. A poor order leaves the building, part way through, with old and new equipment that cannot work together. Four rules prevent that.

Rules for a staging order
RuleWhy
Change each system as a wholeThe indoor and outdoor units of a split, multi-split or VRF system are made to work as a set, and new equipment often runs on a different refrigerant from the system it takes over from. The line between two stages runs between systems, not through the middle of one.
Do the shared work firstA larger electrical supply, a new platform, a new drain route or a new control cable serves every later stage. Done first, in its own window, it stops each changeover waiting on it.
Decide the controls before the first stageOne controller often runs several areas, and old and new systems may not share a controller. Plan how each area is switched on, switched off and scheduled while the building is half changed.
Finish every stage completelyAt the end of each window, every area has working air conditioning from the old system or the new one. No area is left waiting on a later stage unless that was agreed and its temporary arrangement is in place.

Within those rules, the usual order is the shared work, then a low-risk area to prove the method and the timing, then the areas that matter most in the mildest weather available, then the removal of the old plant. A system that is failing goes first, whatever the plan said.

The systems waiting their turn can stay in service. As at November 2026, the Australian Government's phase-down of hydrofluorocarbon refrigerants (opens in a new tab) limits bulk imports of the gas and does not require anyone to take out existing equipment, so a staged plan can run across more than one budget year. Whether an old system is worth keeping that long is a separate question, and the guide to repairing or replacing a commercial air conditioning system covers it.

Temporary arrangements while an area is off

Every area on your map needs an answer for the hours or days it is without air conditioning. Use the simplest arrangement that works.

  • Time it for mild weather. An area that is off on a 20°C day may need nothing else.
  • Keep the old system running until the new one is tested. This works where the new plant goes in a different position, or where one of several systems is changed at a time.
  • Move people. Use a meeting room, another floor or working from home for the days an office is off.
  • Bring in portable heating or cooling. Hired portable units and fans cover a room for a few days. Tell us which rooms, so the power they draw is allowed for.
  • Change the hours. Start earlier in a hot week, or close the affected area for the day.
  • Deal with the sun. Blinds, shade and open windows take the edge off a room during a short outage.

WorkSafe Victoria's code names the same kinds of measures for keeping a workplace at a comfortable temperature: fans, electric heating, open windows, control of direct sunlight, the layout of workstations, clothing, and the pattern of work and rest. WorkSafe also says employers are required by law to consult workers (opens in a new tab) about health and safety matters that could directly affect them. Tell staff what is planned, and ask what would help.

Who is responsible for what

Put a name beside each of these before the first stage. A task with no name is the one that gets missed.

Who usually does what in a staged replacement
TaskUsually falls toSettle beforehand
AccessThe businessKeys, alarm codes, roof access, parking for trucks and a crane, and a contact who answers the phone during each window.
Landlord or building manager approvalThe tenantWhether the lease or the building rules need consent for new plant, roof work or after-hours access, and on what conditions.
Telling staff, customers and neighboursThe businessWhat is off, when, and what the temporary arrangement is. One person sends every notice.
Temporary heating and coolingThe business, with our adviceWhich areas get what, who hires it, and who puts it away.
The asbestos registerWhoever manages or controls the workplaceA copy to the contractor before the site visit.
Electrical workA licensed electricianWhich circuits are isolated in each window. Energy Safe Victoria says all fixed electrical installation work requires a licensed electrician (opens in a new tab).
The refrigerant in the old plantA licensed refrigeration technicianThe refrigerant handling code of practice (opens in a new tab) has all scheduled refrigerant recovered from a system when it is decommissioned, and the equipment labelled to say it has been emptied.
Lifting and trafficThe contractorThe crane, the plan for the lift, any road or footpath consent, and keeping people out from under the load.
Cleaning up at the end of each windowThe contractorCeiling tiles back, floors and exits clear, and the area safe for the people who use it next.
Accepting each stageOne named person for the business, with the technician who did the workWhat is checked and signed before the area goes back into use.

What to check before an area goes back into use

Treat every stage as a small handover. The technician shows the system working, and one person from the business, who knows how the area is used, accepts it. An area goes back into normal use when these are in hand.

Evidence to have before each area reopens
EvidenceWhat it shows
The system runs in cooling and in heatingEach indoor unit serves its area, the controller does what its buttons say, and the water the system makes drains away.
A commissioning recordThe tests run when the new system was started, signed by the technician who ran them.
The old equipment is accounted forIts refrigerant has been recovered and it is labelled as decommissioned, or it is still in service because its stage has not come.
The electrical paperworkA Certificate of Electrical Safety. Energy Safe Victoria (opens in a new tab) says one is required for all electrical installation work. For work that is not prescribed, which it says includes air conditioning, the customer gets a copy within 30 days. Work on the main switchboard is prescribed and is inspected first.
The plumbing paperworkA compliance certificate. In Victoria refrigerated air conditioning work is plumbing work, and under the Building Act 1993 (opens in a new tab) the licensed plumber gives the customer a compliance certificate within five days of finishing work worth $750 or more, counting materials and labour.
Manuals and a logbookInstructions for the people who will use the system, and a logbook where the system needs one.
A list of anything unfinishedWhat is still to do, who does it and by when, agreed before the area is used.

These rules are as at November 2026. The guide to commercial commissioning and handover goes through the tests and the handover documents in full.

If the occupancy permit for your building lists a system this work touches among its essential safety measures, such as an air handling system used to manage smoke, say so before the plan is fixed. The Building and Plumbing Commission (opens in a new tab) says work that alters an existing building may affect its essential safety measures, and that a building surveyor can tell you what has to be done.

Staged replacement plan for a building in use

Staged replacement plan

Fill in what you know, then copy it into your enquiry or print it for the site visit. Leave blank anything you are not sure of.

Your answers stay on this open page. They are not saved or sent. Copy or print them before you leave.

The building and the business

You are the
Landlord or building manager approval

The existing system

Type of system
Where the outdoor plant is

Area 1

Area 1: longest time without air conditioning

Area 2

Area 2: longest time without air conditioning

Area 3

Area 3: longest time without air conditioning

Shutdown windows

Windows that suit the business

People and access

Asbestos register

What staging does to the cost

Staging usually costs more in total and less at any one time. The guide to budgeting for a commercial air conditioning replacement explains why, and sets out every line to allow for.

Who does the work

Replacing a commercial system is licensed work from start to finish. In Australia, work that involves handling a scheduled refrigerant, or a part of the equipment that could release one, needs a refrigerant handling licence (opens in a new tab). You can check any technician's licence at Look for the tick (opens in a new tab).

ABL installs and replaces air conditioning for businesses in Bairnsdale and East Gippsland. Our commercial air conditioning page covers the service, and the enquiry form is on our air conditioning services page. As at November 2026, ABL offers a free site assessment and a free quote. Send your staging plan with the enquiry.

Sources (19)

Planning a replacement around a working business?

Send ABL your staging plan with an enquiry, or call and talk it through.

Filled in the record? Copy or print it first: it is not sent with a call or an enquiry.