Replacing commercial air conditioning while the business stays open
How to stage a commercial air conditioning replacement around a working business: shutdown windows, temporary arrangements, who does what, and a plan to fill in.
Last updated
A commercial air conditioning system can be replaced while the business keeps trading. The work is split into stages, each stage gets an agreed shutdown window, the areas that lose heating or cooling get a temporary arrangement, and each stage is tested and handed over before the next one starts. Fill in the staging plan in this guide before you ask for quotes, so every contractor prices the same job.
How to use this guide
Step 1: Map
List each area, what happens there and how long it can go without air conditioning.
Go to Map the areasStep 2: Plan
Fill in the staging plan: the windows, the temporary arrangements and who does what.
Go to the record
Can commercial air conditioning be replaced while the business stays open?
In most buildings, yes. How much of the building is off at once, and for how long, comes down to a handful of things about the site. We look at each of them on a site visit before we quote.
| What we look at | Why it matters to staging |
|---|---|
| How many separate systems there are | A building served by several independent systems can be changed over one system at a time while the others keep running. A building on one central system loses all of its air conditioning during the changeover, so the window has to be longer or better timed. |
| Where the plant sits | Units on a roof or a plant platform usually need a crane or a hoist, which fixes the day and the hour. Indoor units above desks, counters or stock mean that area is cleared while we work overhead. |
| What the new system can reuse | Ducts, drains, cable routes and platforms that are sound and suit the new equipment shorten each stage. Anything that has to be renewed adds time while the area is off. |
| The electrical supply | New equipment can need a different supply from the old. A licensed electrician does that work, usually before the first changeover so that no stage waits on it. |
| When the building is in use | Trading hours, closed days and quiet seasons decide which windows exist. A seven day business has fewer than an office that shuts at weekends. |
| The time of year | A changeover in mild weather is easier on everyone inside. Around Bairnsdale that means autumn and spring. |
As a guide to the changeover itself, we allow four to six hours to install a standard split system in a home and one to three days for a ducted system. A commercial job takes longer where access is harder, the plant is bigger, or the work has to stop and start around trading.
Map the areas that must stay occupied
Start with a list of every area the system serves. For each one, write down what happens there, when it is in use, and the longest it could go without heating or cooling before the business is affected. That last answer sets the shutdown windows.
| Area | Why it matters | Write down |
|---|---|---|
| Customer areas | A shop floor, dining room, waiting room or reception. Comfort here affects trade, and customers cannot be asked to put up with work overhead. | Trading hours, the quietest day and time, and whether the area can close for a day. |
| Staff work areas | People working at a desk or a counter feel a hot or cold room quickly, and an employer has duties to them. | Who works there, their hours, and where they could work instead. |
| Rooms that must stay cool | A room that holds computer or phone equipment, or stock that spoils in the heat, can need cooling around the clock whether or not anyone is in it. | What is in the room and the temperature it needs. Plan its changeover separately, with its own temporary cooling. |
| Back of house | Storerooms, corridors and rooms used for part of the week can go without for longest, which makes them a good place to start. | The days and hours they are empty. |
| Neighbouring tenancies | Work on a shared roof, a shared plant area or a common wall affects people who are not your staff. | Who they are, and who will tell them. |
For staff areas there is official guidance to plan against. WorkSafe Victoria's compliance code for workplace facilities and the working environment (opens in a new tab) says a workplace where people do seated or desk work should be kept at between 20°C and 24°C, depending on the time of year and the clothing worn, and that employers should consult their employees about comfortable working temperatures. Give a temporary arrangement to any area that would sit outside that range for more than a short window.
Agree the shutdown windows
A shutdown window is an agreed period when the air conditioning in one area is off and the people working on it have the space. A good window is long enough to finish and test the stage, falls when the area is empty or quiet, and has a fallback date in case the weather or a delivery lets it down.
| Window | Suits | Watch for |
|---|---|---|
| Before opening or after closing | A single split system, or one indoor unit at a time. | Short windows suit small stages only, and after-hours work costs more. |
| A weekend or a closed day | A ducted system, or several small systems in one visit. | Access, alarms and lifts on a day the building is shut. A seven day business may have to close one area. |
| A planned closure | A whole-building changeover, or the stage with the longest outage. | Other trades want the same dates, so book early. The guide to planning shutdown work and staged maintenance covers using a closure. |
| During trading, one area at a time | A building with several independent systems, where each area can be closed off or do without for a few hours. | Work overhead, dust and noise next to people. The area under the work is closed while we are in it. |
Pick the season as well as the day. The Bureau of Meteorology's records for Bairnsdale Airport (opens in a new tab) put the average daily maximum at 20.8°C in April, 17.7°C in May, 18.0°C in September and 20.0°C in October, against 25.9°C in January and 14.7°C in July. On average about one day in April and one in October reaches 30°C, against about six in January. A changeover booked for autumn or spring is the least likely to leave an area too hot or too cold.
A window also has to be safe to work in. Settle these before a date is fixed:
- which circuits are switched off and for how long, so nothing else in the building loses power by surprise
- where a crane or a truck will stand, and which entrance, car park or footpath is closed while it lifts
- which rooms and corridors are emptied for the work, and which exits stay clear for everyone else
- when the noisy and dusty work happens, such as drilling and cutting
- who opens up, who holds the keys and alarm codes, and who is phoned if something unexpected turns up
- what happens if the stage cannot be finished in the window: the old system stays in service, or the temporary arrangement carries on
If a crane or a truck has to stand on the street or the footpath, the work may need consent from the road authority. East Gippsland Shire Council has an application for works within the road reserve (opens in a new tab). Ask whoever arranges the lift to confirm what applies, and allow time for it when the date is set.
Have the asbestos register ready too. WorkSafe Victoria says the person who manages or controls a workplace must identify the asbestos in it so far as is reasonably practicable, and that this person or the employer must keep an up to date asbestos register (opens in a new tab) and make it available to contractors who may come across asbestos. In a leased building the structure is usually under the owner's control, so a tenant without a register asks the landlord for one. New pipe and cable routes mean holes through walls, ceilings and roofs, so we ask for the register before the site visit.
Choose a staging order that avoids mismatched systems
The order of the stages matters as much as their timing. A poor order leaves the building, part way through, with old and new equipment that cannot work together. Four rules prevent that.
| Rule | Why |
|---|---|
| Change each system as a whole | The indoor and outdoor units of a split, multi-split or VRF system are made to work as a set, and new equipment often runs on a different refrigerant from the system it takes over from. The line between two stages runs between systems, not through the middle of one. |
| Do the shared work first | A larger electrical supply, a new platform, a new drain route or a new control cable serves every later stage. Done first, in its own window, it stops each changeover waiting on it. |
| Decide the controls before the first stage | One controller often runs several areas, and old and new systems may not share a controller. Plan how each area is switched on, switched off and scheduled while the building is half changed. |
| Finish every stage completely | At the end of each window, every area has working air conditioning from the old system or the new one. No area is left waiting on a later stage unless that was agreed and its temporary arrangement is in place. |
Within those rules, the usual order is the shared work, then a low-risk area to prove the method and the timing, then the areas that matter most in the mildest weather available, then the removal of the old plant. A system that is failing goes first, whatever the plan said.
The systems waiting their turn can stay in service. As at November 2026, the Australian Government's phase-down of hydrofluorocarbon refrigerants (opens in a new tab) limits bulk imports of the gas and does not require anyone to take out existing equipment, so a staged plan can run across more than one budget year. Whether an old system is worth keeping that long is a separate question, and the guide to repairing or replacing a commercial air conditioning system covers it.
Temporary arrangements while an area is off
Every area on your map needs an answer for the hours or days it is without air conditioning. Use the simplest arrangement that works.
- Time it for mild weather. An area that is off on a 20°C day may need nothing else.
- Keep the old system running until the new one is tested. This works where the new plant goes in a different position, or where one of several systems is changed at a time.
- Move people. Use a meeting room, another floor or working from home for the days an office is off.
- Bring in portable heating or cooling. Hired portable units and fans cover a room for a few days. Tell us which rooms, so the power they draw is allowed for.
- Change the hours. Start earlier in a hot week, or close the affected area for the day.
- Deal with the sun. Blinds, shade and open windows take the edge off a room during a short outage.
WorkSafe Victoria's code names the same kinds of measures for keeping a workplace at a comfortable temperature: fans, electric heating, open windows, control of direct sunlight, the layout of workstations, clothing, and the pattern of work and rest. WorkSafe also says employers are required by law to consult workers (opens in a new tab) about health and safety matters that could directly affect them. Tell staff what is planned, and ask what would help.
Who is responsible for what
Put a name beside each of these before the first stage. A task with no name is the one that gets missed.
| Task | Usually falls to | Settle beforehand |
|---|---|---|
| Access | The business | Keys, alarm codes, roof access, parking for trucks and a crane, and a contact who answers the phone during each window. |
| Landlord or building manager approval | The tenant | Whether the lease or the building rules need consent for new plant, roof work or after-hours access, and on what conditions. |
| Telling staff, customers and neighbours | The business | What is off, when, and what the temporary arrangement is. One person sends every notice. |
| Temporary heating and cooling | The business, with our advice | Which areas get what, who hires it, and who puts it away. |
| The asbestos register | Whoever manages or controls the workplace | A copy to the contractor before the site visit. |
| Electrical work | A licensed electrician | Which circuits are isolated in each window. Energy Safe Victoria says all fixed electrical installation work requires a licensed electrician (opens in a new tab). |
| The refrigerant in the old plant | A licensed refrigeration technician | The refrigerant handling code of practice (opens in a new tab) has all scheduled refrigerant recovered from a system when it is decommissioned, and the equipment labelled to say it has been emptied. |
| Lifting and traffic | The contractor | The crane, the plan for the lift, any road or footpath consent, and keeping people out from under the load. |
| Cleaning up at the end of each window | The contractor | Ceiling tiles back, floors and exits clear, and the area safe for the people who use it next. |
| Accepting each stage | One named person for the business, with the technician who did the work | What is checked and signed before the area goes back into use. |
What to check before an area goes back into use
Treat every stage as a small handover. The technician shows the system working, and one person from the business, who knows how the area is used, accepts it. An area goes back into normal use when these are in hand.
| Evidence | What it shows |
|---|---|
| The system runs in cooling and in heating | Each indoor unit serves its area, the controller does what its buttons say, and the water the system makes drains away. |
| A commissioning record | The tests run when the new system was started, signed by the technician who ran them. |
| The old equipment is accounted for | Its refrigerant has been recovered and it is labelled as decommissioned, or it is still in service because its stage has not come. |
| The electrical paperwork | A Certificate of Electrical Safety. Energy Safe Victoria (opens in a new tab) says one is required for all electrical installation work. For work that is not prescribed, which it says includes air conditioning, the customer gets a copy within 30 days. Work on the main switchboard is prescribed and is inspected first. |
| The plumbing paperwork | A compliance certificate. In Victoria refrigerated air conditioning work is plumbing work, and under the Building Act 1993 (opens in a new tab) the licensed plumber gives the customer a compliance certificate within five days of finishing work worth $750 or more, counting materials and labour. |
| Manuals and a logbook | Instructions for the people who will use the system, and a logbook where the system needs one. |
| A list of anything unfinished | What is still to do, who does it and by when, agreed before the area is used. |
These rules are as at November 2026. The guide to commercial commissioning and handover goes through the tests and the handover documents in full.
If the occupancy permit for your building lists a system this work touches among its essential safety measures, such as an air handling system used to manage smoke, say so before the plan is fixed. The Building and Plumbing Commission (opens in a new tab) says work that alters an existing building may affect its essential safety measures, and that a building surveyor can tell you what has to be done.
Staged replacement plan for a building in use
What staging does to the cost
Staging usually costs more in total and less at any one time. The guide to budgeting for a commercial air conditioning replacement explains why, and sets out every line to allow for.
Who does the work
Replacing a commercial system is licensed work from start to finish. In Australia, work that involves handling a scheduled refrigerant, or a part of the equipment that could release one, needs a refrigerant handling licence (opens in a new tab). You can check any technician's licence at Look for the tick (opens in a new tab).
ABL installs and replaces air conditioning for businesses in Bairnsdale and East Gippsland. Our commercial air conditioning page covers the service, and the enquiry form is on our air conditioning services page. As at November 2026, ABL offers a free site assessment and a free quote. Send your staging plan with the enquiry.
Sources (19)
- ABL Refrigeration: air conditioning services (opens in a new tab) ABL's own page. Checked on 19 November 2026.
- WorkSafe Victoria: compliance code, Workplace facilities and the working environment, December 2023 (opens in a new tab) Checked on 19 November 2026.
- WorkSafe Victoria: consultation, reviewed 8 May 2024 (opens in a new tab) Checked on 19 November 2026.
- WorkSafe Victoria: understand and manage asbestos in workplaces, reviewed 9 May 2024 (opens in a new tab) Checked on 19 November 2026.
- Bureau of Meteorology: climate statistics for Bairnsdale Airport (opens in a new tab) Checked on 19 November 2026.
- East Gippsland Shire Council: works within road reserve (opens in a new tab) Checked on 19 November 2026.
- Australia and New Zealand refrigerant handling code of practice, part 2, 2025 edition (opens in a new tab) Checked on 19 November 2026.
- Australian Refrigeration Council: frequently asked questions (opens in a new tab) Checked on 17 November 2026.
- Australian Refrigeration Council: Look for the tick (opens in a new tab) Checked on 17 November 2026.
- Australian Government: hydrofluorocarbon phase-down, updated 4 June 2026 (opens in a new tab) Checked on 17 November 2026.
- Australian Refrigeration Council: ban on high global warming small air conditioning equipment, 2 July 2024 (opens in a new tab) Checked on 17 November 2026.
- Energy Safe Victoria: electrical licence types, reviewed 1 July 2026 (opens in a new tab) Checked on 17 November 2026.
- Energy Safe Victoria: Certificate of Electrical Safety (opens in a new tab) Checked on 17 November 2026.
- Building Act 1993 (Victoria), version of 13 November 2026 (opens in a new tab) Checked on 17 November 2026.
- Building and Plumbing Commission: compliance certificates, updated 9 July 2026 (opens in a new tab) Checked on 17 November 2026.
- Plumbing Regulations 2018 (Victoria), version of 1 May 2026 (opens in a new tab) Checked on 17 November 2026.
- Building and Plumbing Commission: essential safety measures (opens in a new tab) Checked on 19 November 2026.
- NATSPEC: Simple Office Fitout reference specification, April 2025 (opens in a new tab) Checked on 19 November 2026.
- Panasonic Australia: commercial air conditioning range (opens in a new tab) Checked on 19 November 2026.
Related pages
- Commercial air conditioning replacement budget: what to allow
Every cost line to allow for, with a worksheet to fill in from your quotes.
- Commercial air conditioning: repair or replace decision guide
How to weigh a diagnosed repair against a planned replacement.
- Defining a commercial HVAC commissioning handover
The documents and tests to ask for when a new system is handed over.
Planning a replacement around a working business?
Send ABL your staging plan with an enquiry, or call and talk it through.
Filled in the record? Copy or print it first: it is not sent with a call or an enquiry.