Planning HVAC maintenance for an annual shutdown or closed period
How to use a shutdown or closed period for air conditioning maintenance: the jobs to save for it, the order of work, and what to hold before reopening.
Last updated
A shutdown is the one time of year when air conditioning can be switched off and worked on without anyone needing it. Use it for the maintenance that cannot be done properly around people: jobs that need the power off for hours, that make noise or mess, or that are in rooms that are normally full. Plan the work in order, agree in advance what happens if a fault is found, and have the system proven before the doors reopen. The work plan in this guide sets that out.
How to use this guide
Step 1: Choose
Pick the jobs that need a closed building, from the year's service reports.
Go to Jobs for a shutdownStep 2: Plan
Fill in the work plan: areas, dates, order of work and who approves extras.
Go to the recordStep 3: Book
Send the plan with an enquiry well before the closure. Other trades want the same week.
Call (03) 5153 2650
Which air conditioning jobs to save for a shutdown
Not every maintenance task belongs in a shutdown. Routine care, such as filters, has to happen through the year, and saving it for one week defeats its purpose. A shutdown is for the work that an occupied building makes hard.
| Kind of work | Examples | Why a shutdown suits it |
|---|---|---|
| Work that needs the power off for hours | A thorough clean of coils and drain trays, the yearly electrical inspection, and the yearly leak test of the refrigeration circuits. | The unit is out of service while we do it, and water is used close to electrical parts, so the power stays off until everything is dry and closed up. |
| Work in rooms that are normally in use | Cassette and ducted units above desks, counters, beds or stock. Outlets and grilles in meeting rooms and treatment rooms. | We need the floor under the unit clear, and a ladder or a platform where people usually sit. |
| Repairs put off during the year | Parts a service report said were worn, a noisy fan motor, a drain that has blocked more than once. | A part swapped in a planned visit costs less disruption than the same part failing in a busy week. |
| Work that needs a lift | Rooftop plant that needs a crane or a work platform. | The car park and the entrance can be closed off without turning customers away. |
| Changes to controls | New controllers, moved sensors, revised schedules and zones. | The system can be run and tested in every mode without upsetting anyone. |
| A full test | Running each system in cooling and in heating, and checking every zone. | A test in an empty building shows faults that daily use hides. |
The yearly work on a commercial system usually includes cleaning the outdoor coils, more often than yearly on a dusty site, a leak test of the refrigeration circuits, an electrical inspection and a look at the fans. The manual for each model sets the detail, so build the shutdown list from the manuals and from the year's service reports.
Define the areas, the dates and what has to keep running
A closed building is rarely empty and rarely off. Settle these before anyone books a date.
- The dates. The last day of trading, the first day back, and the days in between when nobody will be on site to let a contractor in.
- What still needs cooling or heating. A room with computer equipment, stock that spoils, or anything else that cannot go without for a day.
- Who is still there. Skeleton staff, cleaners, security and other trades, and which rooms they use.
- Other work booked for the same week. Painters, electricians, floor polishers and fitout trades all want a closed building, and a planned power outage for one of them stops work for the rest.
- The outage each area can take. For most rooms in a closed building it is the whole period. For the rooms above, it may be an hour.
Time of year matters as well. A Christmas closure ends in January, which is the hottest month at Bairnsdale: the Bureau of Meteorology's records for Bairnsdale Airport (opens in a new tab) show an average daily maximum of 25.9°C in January, with about six days a month reaching 30°C. A system serviced over that break goes straight back into its hardest work, so the testing at the end matters more than usual.
The order of work
A shutdown plan is a sequence. Each step sets up the next, and the last days are kept clear on purpose.
| Stage | What happens | Who |
|---|---|---|
| 1. Weeks before | The scope is agreed from the makers' schedules and the year's service reports. Parts are ordered. Lifting gear is booked. Staff are told what will be off and when. | You and the contractor |
| 2. First day | Keys, alarm codes and a site contact are handed over. The areas to be worked in are cleared. Rooms that must stay cool get their temporary arrangement before anything is switched off. | You |
| 3. Isolation | The equipment to be worked on is made safe. Switching off, locking off and proving it dead is the technician's job, and nobody else switches it back on. | The technician |
| 4. Outdoor and rooftop work | Plant that depends on the weather or on a lift goes first, so a wet or windy day does not push it past the reopening date. | The contractor |
| 5. Indoor work, room by room | Each room is finished and put back together before the next is opened up: ceiling tiles in, furniture back, floor clean. | The contractor |
| 6. Controls and testing | Each system is run in cooling and in heating. Schedules and set temperatures are put back, because work on a controller can reset them. | The technician |
| 7. Report and walk-through | You are shown what was done and what was found, and given the report. | You and the contractor |
| 8. Spare days | At least one or two working days are left between the end of the work and the reopening, so that a part can still be fetched and fitted. | Built into the dates |
Where a full closure is not possible, the same sequence runs area by area: one system is taken out, worked on, tested and returned before the next one is touched, and each area has its temporary arrangement for the hours it is off.
If something is found: escalation and rollback
Opening up equipment once a year finds things. Decide before the shutdown how those finds are handled, because the person who can approve the money may be on leave when the phone rings.
- Who approves extra work, and up to what amount without a second call.
- How a find is reported. A photo, what it is, what it will cost, and what happens if it is left.
- What is fixed on the spot and what waits. A worn part that is in the van can go in. A part that is weeks away needs a plan.
- The rollback. If a job cannot be finished, the unit goes back to the working state it was in, or it is left off, labelled, with a temporary arrangement for its area. It is not left half done and running.
- Who is told. One person on your side hears about every change to the plan.
Refrigerant leaks have their own rule. The Australian Refrigeration Council says it is illegal to recharge a system before its leaks are tested and repaired (opens in a new tab), so a leak found in a shutdown is repaired in the shutdown or the system stays off. If a find raises the question of whether the unit is worth repairing, the guide to repairing or replacing a commercial air conditioning system covers that decision.
What to have before the building reopens
The evidence that a system is ready comes from the technician who worked on it. Ask for it in writing before the first day back.
| Evidence | What it tells you |
|---|---|
| A service report for each unit | What was done, what was found, the readings taken, and what is recommended. Each one is filed against the unit it belongs to. |
| Confirmation that each system was run and tested | In cooling and in heating, zone by zone, by the technician. |
| The logbook, where the system has one | Brought up to date. The refrigerant handling code of practice (opens in a new tab) has a logbook supplied for a system that holds more than 3 kg of refrigerant, to record maintenance, repairs and any refrigerant added or removed. |
| Paperwork for new electrical or plumbing work | Where the shutdown included installation work. Energy Safe Victoria (opens in a new tab) says a Certificate of Electrical Safety is required for all electrical installation work, and under the Building Act 1993 (opens in a new tab) plumbing work worth $750 or more gets a compliance certificate. |
| A list of what is still open | Parts on order, units left off, and work put back to a later date, each with a name and a date. |
| The schedules for the first day back | The system is set to start by itself on the right day at the right time, so nobody arrives to a building still in holiday mode. |
Keep these records. WorkSafe Victoria's compliance code for workplace facilities (opens in a new tab) says heating and cooling facilities need to be serviced regularly and kept in proper working order, and the report is how you show it was done. If air handling or mechanical ventilation is among the essential safety measures (opens in a new tab) for your building, the Building and Plumbing Commission says the owner must keep records of the maintenance checks and repairs. These rules are as at November 2026.
Maintenance in a business that runs 24 hours
Some workplaces have no shutdown: aged care, accommodation, a service station, a factory on three shifts. The maintenance still has to be done, and the planning replaces the closure.
- Find the quiet hours for each area. A dining room at 3 pm, an office wing on a Sunday, a ward lounge overnight. Windows are set area by area and shift by shift, not for the building.
- Agree the longest outage each area can take, and plan the visit to fit inside it. Several short visits replace one long one.
- Use what the building already has. Where two systems serve one space, one carries the load while the other is serviced.
- Arrange temporary heating or cooling for an area with a single system and people who cannot be moved.
- Plan for night work. Who lets the technician in, who they report to, and which doors and alarms are involved.
- Tell the people on shift. They are the ones in the room when it is off.
For shutdown windows and temporary arrangements for the people in the building, see the guide to replacing commercial air conditioning while the business stays open.
Shutdown work plan
The rest of the year
A shutdown is one entry in a year of maintenance, not a substitute for it. The guide to building a maintenance and reopening calendar covers the other entries, and the guide to commercial maintenance agreements covers what to ask of the provider who does the work.
ABL services and repairs air conditioning for businesses in Bairnsdale and East Gippsland. Our commercial air conditioning page covers the service, and the enquiry form is on our air conditioning services page.
Sources (11)
- ActronAir: installation and commissioning guide, commercial split ducted outdoor unit, version 8 (opens in a new tab) Checked on 19 November 2026.
- ActronAir: installation and commissioning guide, variable capacity commercial ducted indoor unit, version 4 (opens in a new tab) Checked on 19 November 2026.
- Bureau of Meteorology: climate statistics for Bairnsdale Airport (opens in a new tab) Checked on 19 November 2026.
- Australian Refrigeration Council: fact sheet 13, refrigerant leaks, July 2026 (opens in a new tab) Checked on 17 November 2026.
- Australia and New Zealand refrigerant handling code of practice, part 2, 2025 edition (opens in a new tab) Checked on 19 November 2026.
- Energy Safe Victoria: Certificate of Electrical Safety (opens in a new tab) Checked on 17 November 2026.
- Building Act 1993 (Victoria), version of 13 November 2026 (opens in a new tab) Checked on 17 November 2026.
- WorkSafe Victoria: compliance code, Workplace facilities and the working environment, December 2023 (opens in a new tab) Checked on 19 November 2026.
- WorkSafe Victoria: consultation, reviewed 8 May 2024 (opens in a new tab) Checked on 19 November 2026.
- Building and Plumbing Commission: essential safety measures (opens in a new tab) Checked on 19 November 2026.
- ABL Refrigeration: air conditioning services (opens in a new tab) ABL's own page. Checked on 19 November 2026.
Related pages
- Business air conditioning pre-summer maintenance calendar
How the shutdown fits into a year of maintenance.
- Commercial air conditioning maintenance agreement questions
What to ask of the provider who does the work.
- Commercial air conditioning replacement in an occupied building
Shutdown windows and temporary arrangements for a building in use.
Planning work for a closed period?
Send ABL your shutdown work plan with an enquiry, or call well before the closure.
Filled in the record? Copy or print it first: it is not sent with a call or an enquiry.