Budgeting for a commercial air conditioning replacement

The cost lines a commercial air conditioning replacement budget needs beyond the equipment, what moves each one, and a worksheet to fill in from your quotes.

Last updated

A budget for replacing commercial air conditioning needs more lines than the price of the equipment. Allow for the plant, the electrical work, access and lifting, building work, removal of the old system, commissioning and paperwork, the years of maintenance and running costs that follow, and a contingency for what nobody can see until the job starts. The worksheet in this guide sets those lines out, to fill in from your quotes.

How to use this guide

  1. Step 1: Learn the lines

    Read what each cost line covers and what moves it.

    Go to Cost lines
  2. Step 2: Fill in the worksheet

    Enter each line from your quote, and note what the quote leaves out.

    Go to the record
  3. Step 3: Ask about the gaps

    Call with the worksheet open, or paste it into an enquiry.

    Call (03) 5153 2650

How much does it cost to replace commercial air conditioning?

It depends more on the building than on the equipment. Two shops can fit the same units and get quotes that are far apart, because one has a crane lift, an old switchboard and a ceiling full of other services, and the other has none of those.

ABL publishes guide prices for homes, and none for commercial work. As at November 2026, the home guide is $2,000 to $4,000 for a basic split system installed, and from $7,000 to $15,000 or more for a ducted system, depending on the size of the home and its zoning. There is no commercial guide because the lines in the table below decide the price, and they differ from one building to the next. Your quote is the price, and we look at the site before we give one.

The cost lines in a commercial replacement budget

These are the lines a complete budget carries. A quote may roll several into one figure. Ask for them to be shown separately, so you can see what is in and what is out.

Budget lines for a commercial air conditioning replacement
LineWhat it coversWhat moves it
PlantThe outdoor and indoor units and their controllers.The capacity the building needs, the number of indoor units, and the type of system: wall splits, cassettes, ducted, multi-split or VRF.
Pipework, ducts and drainsThe refrigerant pipes, the ducts and outlets, and the condensate drains.How much of the existing run suits the new equipment and tests sound, and how far the new units are from the old ones.
Electrical workSupply circuits, isolating switches, control wiring and any work on the switchboard.Whether the existing supply and switchboard can carry the new plant. An upgrade to either is a job in itself, done by a licensed electrician.
Access and liftingA crane, a hoist, scaffolding or a work platform, and the labour to move plant through the building.Roof height, how close a crane can stand, whether the street or footpath has to be used, and whether the lift has to happen out of hours.
Building workPlatforms and plinths, roof and wall penetrations and their weatherproofing, ceiling access, patching and painting.The age and construction of the building, and whether the new plant sits where the old plant sat.
Removal and disposalRecovering the refrigerant, taking the old plant down and out, and disposing of it.The size of the old plant and how it comes off the roof. Refrigerant recovery is licensed work.
Design and approvalsThe heat load calculation and layout, drawings, and any permits or consents.The size of the job, and whether a landlord, a building surveyor or the council has to be involved.
Commissioning and handoverStarting and testing the system, setting the controls, showing your staff how to use it, and the paperwork.The number of systems and zones, and how much of the handover is spread across stages.
Staging and temporary arrangementsExtra visits, out-of-hours labour, and temporary heating or cooling while an area is off.How many stages there are, and how long each area can go without.
MaintenanceScheduled servicing from the first year on.The number of units, how hard they work, and how exposed the site is.
Running costThe electricity the new system uses.Its efficiency, the hours it runs and how it is controlled.
ContingencyYour own allowance for what turns up once work starts.How much of the building was seen and opened before the quote was written.

Three of those lines carry rules worth knowing when you read a quote. The refrigerant in the old plant has to be recovered by a licensed technician when the system is decommissioned, as the refrigerant handling code of practice (opens in a new tab) sets out, so a removal price that seems too low may have left it out. A Certificate of Electrical Safety is required for all electrical installation work, as Energy Safe Victoria (opens in a new tab) explains, and work on the main switchboard is independently inspected first. The Building and Plumbing Commission (opens in a new tab) says all building work requires a building permit unless the regulations exempt it, and suggests asking your council or a building surveyor whether your project needs one.

What are provisional items, and why keep a contingency?

A provisional item is an allowance in a quote for work whose extent cannot be known until the job is under way. Victoria's law on home building contracts defines a provisional sum as a reasonable estimate of the cost of carrying out work that cannot be given a definite price when the contract is signed, as Consumer Affairs Victoria (opens in a new tab) explains, and commercial quotes use the term in the same sense. You pay what the work turns out to cost, which can be more or less than the allowance.

A provisional item is fair when it is honest about an unknown, and a problem when it hides one. For each provisional item in a quote, ask three things: what would trigger it, how the cost is worked out if it is triggered, and what could be inspected now to turn it into a fixed price.

A contingency is different. It is your money, held in your budget, for the things no quote lists. On a replacement these are the usual reasons to hold one:

What a contingency is usually spent on
What turns upWhy it was not in the quote
The electrical supply is too smallThe capacity of the supply and the state of the switchboard are not always clear until an electrician tests them.
Asbestos in a wall, ceiling or roofNew pipe and cable routes mean new holes. WorkSafe Victoria says asbestos likely to be disturbed must be identified before refurbishment work starts (opens in a new tab), and dealing with it is separate work.
Pipes, ducts or drains that cannot be reusedA run hidden in a ceiling or a wall can be damaged, undersized or in the way, and that shows only when it is opened up or tested.
The roof or platform needs workNew plant can be a different size and weight from the old, and corroded steel or a weak roof sheet shows when the old plant comes off.
Access is harder than it lookedA crane cannot stand where planned, or the plant will not pass through a door, a stair or a ceiling hatch.
Days lost to weatherRoof work and crane lifts stop for wind and rain.

There is no single right percentage for a contingency. Hold more where less of the building has been seen: a site visit that included the roof, the ceiling space and the switchboard leaves fewer surprises than a quote written from photos.

What should a commercial quote say it includes?

A price means little until you know what it assumes. Get these in writing with every quote, and copy them into the worksheet:

  • The design basis. The areas served, the number of people and the equipment allowed for in each, and the capacity chosen.
  • The equipment. Brand, model and capacity of every unit and controller.
  • What is reused. Which pipes, ducts, drains, platforms and cables stay, and on what condition.
  • The electrical work. What is included, what is left to your own electrician, and who pays if the supply needs upgrading.
  • Access and hours. The lifting method, the working hours priced, and the number of visits.
  • Removal. Whether the old plant is taken away, and whether refrigerant recovery is in the price.
  • Commissioning and handover. The tests, the documents you will be given, and who is shown how to run the system.
  • Warranty. The terms on the equipment and on the installation, in writing.
  • After handover. Whether the first service is included, and what a maintenance agreement would cost.
  • The price basis. Whether each figure includes GST, and how long the quote stands.

Two guides take these further: the guide to comparing commercial air conditioning quotes lines quotes up against each other, and the guide to defining a commercial commissioning handover lists the handover documents.

How staging changes the budget

Replacing a system in stages usually costs more in total and less at any one time. Each stage has its own set-up and its own handover, a crane may come more than once, and work fitted around trading runs into evenings and weekends. Against that, the spending can be spread across budget years, the business keeps trading, and the first stage shows what the rest will really cost.

If you stage the work, budget each stage as its own column. The guide to replacing commercial air conditioning while the business stays open explains how to plan the stages, and which work comes first.

The costs that come after installation

A replacement budget that stops at handover misses the costs that decide whether the new system lasts. Budget for servicing from the first year: at least one visit a year, and two where the system runs daily or the site is near the coast. The guide to comparing commercial maintenance agreements covers what an agreement should include.

Running cost usually moves the other way. New equipment is generally more efficient than the equipment it takes over from, so it can be cheaper to run. How much cheaper depends on the old system, the hours and the controls, so treat any saving in a quote as an estimate and ask how it was worked out.

Check for a discount before you sign. As at November 2026, the Victorian Energy Upgrades program (opens in a new tab) offers discounts on approved high-efficiency reverse-cycle air conditioners to businesses as well as households, subject to conditions. The upgrade has to be done by an accredited provider or an installer working with one, and the accredited provider confirms whether a job is covered and what the discount is. Contact one before you buy, because discounts are typically not applied afterwards.

If the budget does not stretch to a replacement this year, the guide to repairing or replacing a commercial air conditioning system covers how to weigh a repair that buys time.

Replacement budget worksheet

Commercial air conditioning replacement budget

Fill in one worksheet for each quote. Write "not shown" where a quote does not separate a line, and ask for it.

Your answers stay on this open page. They are not saved or sent. Copy or print them before you leave.

The quote

Prices are shown

Equipment and installation

Provisional items and contingency

Staging

Out-of-hours work is priced in

What the quote assumes

After installation

Discount checked with an accredited provider

Totals

Getting a quote you can budget from

The fastest way to a budget that holds is a site visit that covers the roof, the ceiling space and the switchboard, with someone there who knows the trading hours and the access. Fewer unknowns means fewer provisional items.

ABL installs and replaces air conditioning for businesses in Bairnsdale and East Gippsland. Our commercial air conditioning page covers the service, and the enquiry form is on our air conditioning services page. As at November 2026, ABL offers a free site assessment and a free quote.

Sources (14)