Moving a modular coolroom to a new site: what to plan and record
What to record before a modular coolroom comes apart, how to compare the old and new sites, who does each part, and how to keep stock cold through the move.
Last updated
A modular coolroom can be taken down and rebuilt on a new site, but not every room comes through a move unchanged. Whether its panels, door and plant go up again depends on their condition, on the new site and on what the room will do there. Before anything comes apart, record what the room is made of and the state it is in, compare the old site with the new, and plan where your stock goes while the room is out of service. Taking the room down, the refrigeration and the wiring are trade work. This guide is for the business planning the move.
How to use this guide
Step 1: Record the room
Its panels, door, plant, plate and papers, before anything moves.
Go to InventoryStep 2: Fill in the relocation plan
The old site against the new, and where the stock goes.
Go to the record
Can the room be reused as it is?
The condition of the panels decides more than anything else. Panels with water in them, or damage across the room, are a poor base for a rebuild. A room is checked part by part, and this is what we look at.
| Part | What we look at | What can rule it out |
|---|---|---|
| Wall and ceiling panels | The metal skins, the joints, and the base of each wall where water collects. | Water in the insulation, which can show as bulging or corrosion. Punctures, and skins coming away from the core. |
| Joints | How the panels are joined. Most makers use a slip joint that is sealed on site, and some rooms use cam-locks that release with a key. | Joints that cannot be parted without damaging the panel edges, and cam-locks rusted fast. A lock that cannot be released without breaking it can cost the panels on both sides. |
| Floor | Whether the room sits on insulated floor panels, an insulated slab or the building's floor. | A slab stays where it is. Floor panels are judged on their condition like the walls. |
| Door | The hinges, the seals, the inside release and, on a freezer, the door heater. | Damage, or a release that does not work. |
| Refrigeration plant | Its age, the details on its plate, its logbook and how it has run. | Age, or a load at the new site it was not chosen for. |
| Cut-outs | Where the panels are cut for the plant, pipes and drain. | A different unit at the new site may not fit the old openings. |
If the plant is old, a move is a good time to ask whether to replace it. The federal government's energy guide for refrigeration (opens in a new tab) says a system more than 10 years old should be considered for replacement, and that an efficient new system could save up to 30% in energy use.
If the room will be colder at the new site, it is a different room. A freezer needs thicker panels than a coolroom, at least R6 against at least R4.5, and an insulated floor, so a chilled room does not simply become a freezer by moving it. Panel and plant warranties carry their own conditions, so ask the panel maker or supplier, and the plant's, how a move affects them before you count on them.
What to record before anything comes apart
Once panels are stacked on a truck, what they were is hard to tell. Photograph and write down these before the move. None of it means opening anything.
| What to record | Where to find it, and why |
|---|---|
| The plant's identification plate | Photograph it. The refrigerant handling code (opens in a new tab) asks for a plate on or near the system showing who installed or made it, the model and serial number, the year, the refrigerant and how much the system holds. |
| Any later labels on the plant | A change of refrigerant or oil is recorded on a label with the technician, their licence number and the date. |
| The logbook | A system holding more than 3 kg of refrigerant comes with a logbook of its maintenance and repairs. Find it and keep it with the room. |
| Manuals and commissioning papers | The operating and maintenance instructions, the commissioning data and any test certificates. They tell the technician at the new site how the system was set up. |
| Panel labels and layout | Some makers mark and number each panel at the factory. Photograph every label, and sketch where each panel sits. |
| Panel thickness and core | From the labels or the original quote. It says what temperature the room was built for. |
| How the plant gets power | Whether it plugs into a power point or is wired in. Wired-in plant is disconnected from the fixed wiring, and connected at the new site by a licensed electrician. |
| Damage you can see | Bulges, dents, punctures, rust, peeling skins, gaps at the base of the walls. Photograph each one. |
| Door safety features | Whether the inside release, the inside light switch, the outside lamp and the alarm all work now, so a fault is not put down to the move. SafeWork SA (opens in a new tab) advises keeping the inside door release in good working order and the emergency alarm tested regularly. |
| The last service | When, who, and any fault still open. |
Comparing the old site with the new
The new site decides how much of the room can go up again unchanged, and whether the plant still suits. Note each of these for both sites.
| Compare | Why it matters |
|---|---|
| Footprint and height | The same length, width and height lets more of the panels go back as they were. A different shape means new or cut panels. |
| The floor | Level and firm for the room, and insulated if the room is a freezer. |
| The way in | Panels and plant have to be carried in. Note the narrowest doorway and the tightest corner. |
| Power | Single-phase or three-phase, and how far it is from the switchboard to the room. The plant's plate says what it needs. |
| Where the plant's heat goes | A unit chosen for one site can be too small on a hot roof, in a poorly ventilated corner or in a hot plant room. |
| Pipe run | For a split system, the distance between the two units. Keep it short. |
| Drain | Where water from the evaporator can run to. |
| How the room will be used | More door openings, warm product or longer hours at the new site need more cooling capacity. |
| Room to service the plant | Access around it for maintenance, repair and inspection. |
At the new site the room still has to meet the National Construction Code 2025 (opens in a new tab), clause G1D3, and the coolroom installation page lists what it asks for. The lamp, the alarm and the inside switch are wired and checked again.
Ask a building surveyor whether the rebuilt room needs a building permit, and check the food business's registration or licence for the new site. The guide to converting a storeroom into a coolroom sets out who issues building permits in East Gippsland and who registers or licenses a food business. If the room is leaving leased premises, see the guide to installing a coolroom in leased premises for the make good side. For where the room should stand at the new site, see the guide to an indoor or outdoor coolroom.
Who does each part of the move
| Part of the move | Who does it |
|---|---|
| The refrigeration plant | A licensed refrigeration technician. Work that involves handling a scheduled refrigerant, or a part of the equipment that could release one, needs a refrigerant handling licence. |
| Wiring at both sites | A licensed electrician. All fixed electrical installation work needs one in Victoria, and the electrician gives you a Certificate of Electrical Safety for the work, as Energy Safe Victoria (opens in a new tab) explains. |
| Panels and door, down and up | The coolroom contractor. |
| Moving the parts between sites | Whoever the quote names. Agree it in writing, with who is responsible for the panels while they travel and wait. |
| Making good the old site | You, with the landlord if you lease. The Victorian Small Business Commission (opens in a new tab) suggests agreeing in writing what has to be removed or repaired. |
At the new site, a system with pipework joined on site is leak tested before refrigerant goes back in: the refrigerant handling code asks for a leak tightness test after a system is moved. That test is for systems put together on site, not for a factory-sealed one-piece unit. Every test is documented, and the refrigerant added is recorded in the logbook.
If the panels have to wait between sites, ask where. Panels are kept dry and covered, and stacked so water drains off them, or the damage this guide began with can start in storage.
Keeping stock cold through the move
From the day the room is shut down until it is back at temperature on the new site, its stock needs somewhere else to be. Potentially hazardous chilled food is kept at 5°C or below, unless the business can show another temperature is safe, and frozen food stays frozen hard. Choose where it goes before the dates are set:
- sell or use the stock down before the room shuts
- hire cold storage for the gap: ABL hires out coolrooms, and the coolroom hire page has the details
- use storage at another of your sites
- hold it in a refrigerated vehicle
When stock moves, Food Standards Australia New Zealand (opens in a new tab) advises keeping the trip as short as you reasonably can, keeping cold food at 5°C or colder in insulated containers or refrigerated equipment, and checking it with a thermometer. Safe Food Australia adds that a business with more than one premises needs a thermometer at each, accurate to plus or minus 1°C. Log the temperatures wherever the stock is held: see the guide to a temperature record sheet for a coolroom.
The order things happen in
| Step | What happens | Who |
|---|---|---|
| 1. Stock out | Stock sold down or moved to its holding place, already cold, with a thermometer there. | You |
| 2. Plant made safe | The refrigeration is shut down and dealt with as the code requires, and the logbook updated. | Licensed refrigeration technician |
| 3. Power off | Wired-in plant and the room's wiring are disconnected. | Licensed electrician |
| 4. Room down and moved | Panels and door taken down, checked as they come apart, moved and stored dry. | Coolroom contractor |
| 5. Old site made good | As the lease or the owner requires. | You, with the landlord |
| 6. Room up at the new site | Panels and door rebuilt and sealed, and the plant set in place. | Coolroom contractor |
| 7. Power on | Connection at the new site, with a Certificate of Electrical Safety for the work. | Licensed electrician |
| 8. Tests | Strength and leak tightness tests on site-assembled pipework before refrigerant goes in, and the safety devices tested. | Licensed refrigeration technician |
| 9. Start-up | We bring the room down to temperature and watch it run through at least two cycles, checking the defrost and the drain. | Technician |
| 10. Room checks | Door release, inside light switch, outside lamp and alarm all checked again. | Technician and you |
| 11. Stock back in | Once the room holds its temperature on a calibrated thermometer. | You |
| 12. Papers | Commissioning checklist and data, test records, logbook entries and the Certificate of Electrical Safety kept with the room. | Technician, electrician and you |
What drives the cost and the downtime of a move?
A move is priced on the room and both sites. These are the things that add to it:
| What | Why it adds to the job |
|---|---|
| A different footprint or height | New or cut panels, so the room is no longer a straight rebuild. |
| Old plant | Plant near the end of its life may be replaced rather than moved. |
| A split system | New pipework between the two units at the new site, and the strength and leak tightness tests before refrigerant goes back in. |
| Electrical work at both sites | Disconnection at the old site and connection at the new, each by a licensed electrician. |
| Making good the old site | Whatever the lease or the owner requires once the room is out. |
| Storage between sites | Somewhere dry for the panels if they cannot go straight from one site to the other. |
| Cold storage for the gap | Hire, or room at another site, for as long as the room is out of service. |
The downtime runs from step 1, stock out, to step 11, stock back in. New panels, new pipework, a building permit or new power at the new site each add to it. Ask for the quote to state how many days the room will be out of service, and write that in the plan. The coolroom installation page says how long a panel build usually takes.
Coolroom relocation plan
Planning the move with ABL
ABL's modular panel rooms can be relocated or expanded as a business grows. Send the relocation plan with your enquiry, or have it in front of you when you call, and tell us both addresses. The coolroom installation page explains what a site needs and how a build runs.
Sources (21)
Checked on 19 November 2026
- Australia and New Zealand refrigerant handling code of practice, part 2, 2025 edition (opens in a new tab)
- Australian Refrigeration Council: frequently asked questions, refrigerant handling licence (opens in a new tab)
- Energy Safe Victoria: Restricted Electrical Worker licence, reviewed 1 July 2026 (opens in a new tab)
- Energy Safe Victoria: Certificate of Electrical Safety (opens in a new tab)
- Australian Building Codes Board: National Construction Code 2025, Volume One, Part G1, clause G1D3 (opens in a new tab)
- Food Standards Australia New Zealand: storing food safely (opens in a new tab)
- Food Standards Australia New Zealand: transporting food safely (opens in a new tab)
- Food Standards Australia New Zealand: the 2-hour/4-hour rule, updated 30 September 2025 (opens in a new tab)
- Food Standards Australia New Zealand: Safe Food Australia, chapter 3.2.2 (opens in a new tab)
- SafeWork SA: cold storage facilities (opens in a new tab)
- Victorian Small Business Commission: preparing for end of lease, updated 30 June 2023 (opens in a new tab)
- Australian Government, energy.gov.au: refrigeration guide for businesses (opens in a new tab)
- Danfoss: cold room system design and component selection (opens in a new tab)
- BlueScope: technical bulletin 31, COLORBOND Intramax steel for coolroom panels, December 2020 (opens in a new tab)
- KPS Global: what to consider when modifying a walk-in, 18 March 2025 (opens in a new tab)
- Kingspan: cold store and freezer chambers, cam-lock assembly instructions, 2024 (opens in a new tab)
- Kingspan Paroc Panel System: handling instructions for elements (opens in a new tab)
- Bondor: MetecnoPanel PIR information guide, February 2016 (opens in a new tab)
- Bromic: modular coldroom installation manual, May 2005 (opens in a new tab)
- Heatcraft: installation and operations manual for condensing units, September 2026 (opens in a new tab)
- ABL Refrigeration: commercial refrigeration services (opens in a new tab) ABL's own page.
Related pages
- Installing a coolroom in leased premises: the permission and project brief
For the make good side when a room leaves leased premises.
- Indoor or outdoor coolroom: choosing a location
Where the room should stand at the new site.
- Commercial refrigeration temperature records and template
Log the stock while it is held elsewhere.