Coolroom installation and freezer rooms in East Gippsland

ABL installs coolrooms and freezer rooms in East Gippsland. Plant types, sizing, what the site needs, the stages of a build and what drives the cost.

Send an enquiry with the project brief on this page, or call ABL. We look at the site, then quote the room, its refrigeration and its fitout. To start, have a rough idea of what you store and how much of it.

How a coolroom project runs

  1. Step 1: Write the brief

    What you store, how cold, where the room would go and what is in the way.

    Go to the record
  2. Step 2: Site assessment

    We look at the floor, the height, the way in, the power and the drainage.

    Go to What the site needs
  3. Step 3: Quote

    We quote the room, its refrigeration and its fitout for your site.

    Call (03) 5153 2650

What ABL installs

  • Chilled, frozen or both. Coolrooms, freezer rooms, and rooms with a chilled side and a frozen side.
  • Modular panel rooms. From about 5 cubic metres to more than 100. A modular room can be moved or made bigger later.
  • New rooms and retrofits. In a new building, or fitted into one you already have.
  • Fitout. Shelving, strip curtains, lighting, and temperature monitoring with alarms.

An installation takes in the assessment of the site, the design of the refrigeration and the assembly of the panels. Any fixed wiring the room needs is electrical installation work, which in Victoria requires a licensed electrician, as Energy Safe Victoria (opens in a new tab) sets out.

If you only need cold storage for a while, see the coolroom hire page. If a room you already have has failed, see the coolroom and commercial fridge repairs page. Our other work is on the commercial refrigeration page.

Coolroom or freezer room?

How a coolroom and a freezer room differ
PointCoolroomFreezer room
What it holdsChilled food and produce.Frozen stock.
What the food standards askPotentially hazardous chilled food at 5°C or below, unless a business can show another temperature is safe (Safe Food Australia, chapter 3.2.2 (opens in a new tab)).Frozen food stays frozen. The standard gives no temperature as a number.
Typical design temperatureUsually 0 to 4°C.Usually minus 18°C to minus 20°C. That is common practice, not a figure from the food standards.
PanelsThe federal government's energy guide for refrigeration (opens in a new tab) recommends at least R4.5, which it gives as 140 mm of rigid foam.The same guide recommends at least R6, which it gives as 175 mm.
FloorCan usually sit on a level floor.Needs an insulated floor or slab. Under a freezer the ground can freeze, expand and lift the floor, which is why heating is sometimes laid below the floor insulation.
Ramp at the doorMany need none.A ramp is common.
DrainThe drain line from the evaporator falls through a trap to an open drain.The same, and the line may need a heater so it does not freeze.
What to tell usWhat you store, and whether any of it needs a temperature of its own.What you store, how long you hold it, and what your suppliers or customers ask for.

A room can also be built with a chilled side and a frozen side. Tell us how much of each you need, and which side you walk into most.

The panel figures are a recommendation for low running cost, not a rule. Ask what panel thickness a quote allows for.

Before frozen storage is added to a site, and before anything is ordered, the site assessment looks at whether the electrical supply of the building can carry it. Have the location of your switchboard ready, and the name of your electrician if you have one.

What temperature do different goods need?

The setting is yours to choose, with your food safety program and your customers. The first two rows are the food standards, as Food Standards Australia New Zealand (FSANZ) explains them (opens in a new tab). The rest are the best storage conditions for each crop, from the Australian vegetable industry's postharvest guide (opens in a new tab).

Storage temperatures by kind of goods
GoodsTemperatureLaw or practice
Potentially hazardous chilled food5°C or colder.The food standards
Frozen foodFrozen hard. The standards give no figure.The food standards
Broccoli, cauliflower, cabbage, carrots and sweet corn0°C, at 95 to 100% humidity.Recommended practice
Baby spinach, lettuce and celery2°C, at 95 to 100% humidity.Recommended practice
Green capsicum2 to 5°C, at 90 to 95% humidity.Recommended practice
Beans7 to 10°C, at 90 to 95% humidity.Recommended practice
  • One room cannot suit everything. Broccoli is best at 0°C and beans at 7 to 10°C, so tell us everything that will share the room.
  • A few degrees change the result. Broccoli keeps about 6 weeks at 0°C and 2 to 3 weeks at 5°C.
  • Colder than needed costs money. Set the room no colder than the goods need.

For how a display reading relates to the food itself, see the guide to food temperature and fridge readings.

Drop-in, split or rack: which refrigeration plant suits?

Three arrangements cover most rooms. A one-piece unit is also sold as a drop-in, a slide-in or a monoblock, depending on the maker.

Three ways to refrigerate a cold room
ArrangementWhat it isWhat it suits
One-piece unitEverything is in one housing, charged with refrigerant at the factory and mounted on a wall, a door panel or the ceiling of the room. No refrigerant pipes are run on site.Small and medium rooms. Its warm air leaves from the side that faces out of the room, so that space needs air moving through it.
Split systemThe work is divided between two units. The condenser sits outside or in a plant room, the evaporator sits inside the cold room, and refrigerant pipes run on site join the two.Larger rooms and sites with a big cooling load.
Multi-compressor rackTwo to five compressors built as one factory package.Supermarkets, cold storage facilities and industrial process cooling.

The match matters in both directions. An underpowered unit struggles to hold temperature, and an oversized one short-cycles and wears out faster. We decide which arrangement suits your room at the site assessment. Tell us:

  • what is above and beside the place the room would go
  • whether there is an outside wall, a yard or a plant area close by
  • whether warm air coming off the side of the room would be a problem where it stands
  • how big the room is likely to be

For the choice between a room inside the building and one outside it, see the guide to an indoor or outdoor coolroom.

What decides the size of the room and the plant?

We size the refrigeration to the heat it has to take out of the room in a day. Four kinds of heat add up to that figure, and a safety margin goes on top.

Where the heat in a cold room comes from
Where the heat comes fromWhat changes itWhat to tell us
Through the walls, floor and ceilingThe size of the room, its insulation, and how warm it is around the room.Where the room would stand, and how hot that spot gets.
Through the doorHow often the door opens. A busy door can double this part of the load.How many times the door opens on a busy day, and for how long.
The productHow much goes in each day and how warm it is. Cooling it in half the time doubles this part of the load. Fresh fruit and vegetables also give off heat of their own in storage.What you store, how much arrives on a busy day, and its temperature when it goes in.
Lights, motors and peopleLighting, fan motors, glass doors and the people working in the room.How the room is used: who goes in, how often, and for how long.

Bigger is not safer. An oversized room costs more to build and more to run, so plan for what the business needs now and in the next few years.

The size of the room itself comes from your own numbers: what you store, how much of it at your peak, how it arrives, and how often it turns over. Put those in the brief and we work the size out with you. If you are still deciding whether a room is the right answer, see the guide to a coolroom or commercial fridges.

How a coolroom installation runs, stage by stage

Every site differs, but the order is much the same.

The stages of a coolroom or freezer room installation
StageWhat happens
1. Assessment and designWe measure the site, then design and quote the room, its refrigeration and its fitout.
2. FloorWe check the floor for level. A freezer room gets an insulated floor or slab.
3. PanelsWalls and ceiling go up together, starting from one corner. The joints are fitted tight and sealed to keep moisture out.
4. DoorThe door is hung once the shell is standing, and a ramp is fitted if the room needs one.
5. RefrigerationA one-piece unit is mounted on the room. A split system has its evaporator hung inside, not over the door, and its condensing unit set outside or in a plant area.
6. DrainThe drain line from the evaporator is run with a fall, through a trap, to an open drain. It is not joined directly to the sewer, and local plumbing rules govern.
7. ElectricalA licensed electrician connects the fixed wiring.
8. Start-up and handoverWe bring the room down to temperature and check it before stock goes in. You are handed its instructions and records.

The panel build usually takes from a day for a small room to about two weeks for a large or complex one. That covers the panels only, so ask us about the timing of your own job.

What the site needs: power, floor, drainage and access

The site assessment settles the things a drawing cannot. You can make it quicker by having these ready.

What the site needs and what the assessment looks at
What we look atGeneral guidanceWhat to have ready
The floorA coolroom can usually sit on a level floor. A freezer room needs an insulated floor or slab.What the floor is made of, and what is under it if you know.
HeightWe confirm overhead clearance for the full height of the room before a wall panel goes up. Above about 2.4 metres the build needs lifting equipment.The lowest point of the ceiling where the room would go, and anything that hangs below it: beams, ducts, lights or sprinklers.
The way inPanels and equipment have to be carried in, and a part may have to come out again if it is replaced.The narrowest doorway and the tightest corner on the route, and any steps, ramps or lifts.
Air and room to workA one-piece unit pushes its warm air out beside the room. A condenser belongs where air moves freely, away from other heat. The refrigerant handling code of practice (opens in a new tab) says designers should give safe access to the entire plant for maintenance.What is around and above each place the refrigeration could go.
PowerFixed wiring is electrical installation work, which in Victoria requires a licensed electrician. What supply a room needs depends on its refrigeration, so the assessment works it out.Where the switchboard is, whether the supply is single-phase or three-phase if you know, and your electrician if you have one.
DrainageWater from the evaporator needs an open drain it can fall to. In a freezer room the line may need a heater so it does not freeze.Where the nearest floor waste or drain is.

What does the building code ask of a walk-in room?

The National Construction Code (opens in a new tab), Volume One, clause G1D3, covers a refrigerated or cooling chamber that is big enough for a person to enter. It asks for:

  • a door that can be opened by hand from the inside without a key
  • a doorway with a clear width of at least 600 mm and a clear height of at least 1.5 m
  • lighting inside, worked only by a switch inside the room beside the door
  • a lamp outside the room that is lit when the lights inside are on
  • an alarm that can be set off only from inside the room and sounds outside it, at 90 dB(A) measured 3 m from the sounder

The guide to the code says the aim is to stop people being locked in a space meant for short visits. SafeWork SA (opens in a new tab) adds that the inside door release should be kept in good working order and the emergency alarm tested regularly. Volume One covers Class 2 to 9 buildings, so ask your building surveyor how the clause applies to a farm shed.

Fitout options and what each is for

Fitout options for a coolroom or freezer room
OptionWhat it is for
ShelvingKeeps stock in order, with gaps so chilled air can circulate.
Strip curtains and fast-closing doorsStrip curtains cut the heat that comes in through an open doorway. A room that is entered all day is better with an automatic fast-closing door.
LightingThe building code asks for lighting switched from inside the room. Use LED lighting where you can.
Temperature monitoring and alarmsA record of the room temperature, and a warning when it drifts. See the temperature monitoring page.

What drives the cost of a coolroom?

A quote is for your room on your site, so this page gives no price. These are the things that move the figure.

What moves the price of an installed room
What moves the priceWhy
SizeMore panel, a bigger floor and more refrigeration.
TemperatureA freezer room takes thicker panels than a coolroom of the same size, and an insulated floor.
What goes in, and how warmWarm product and a busy door add heat, so the refrigeration is bigger than for a room that only holds cold stock.
The plant and where it goesA one-piece unit has no pipes to run on site. A split system has pipework between its two units, and a long run adds to it.
Site workWhat the floor, the power, the drainage and the way in need before the room goes up.
FitoutShelving, strip curtains, lighting, monitoring and alarms.
New or retrofitFitting a room into an existing building, or building it into a new one.

What keeps the running cost down?

The federal government's energy guide for refrigeration (opens in a new tab) puts the average potential energy waste of a walk-in cool room or freezer at over 25%. These are the things that stop it.

  • Seal the room well. Even small gaps between panels, or around pipes that enter a wall, let warm, moist air in.
  • Keep cold air in at the door, with strip curtains and an evaporator that does not blow straight out of the doorway.
  • Put the condenser where air moves freely and away from other heat.
  • Set the room no colder than the goods need.
  • Do not build bigger than the business needs.

When you have more than one quote in hand, see the guide to comparing commercial refrigeration quotations.

Your project brief

Coolroom project brief

Fill in what you can. A gap is fine: it tells us what to look at on site. Then paste it into an enquiry or read it out when you call.

Your answers stay on this open page. They are not saved or sent. Copy or print them before you leave.

What you store

Temperature and layout

Kind of room
Where it would go

The site

The building is
You
Power supply
A floor waste or drain close by

Fitting a room into an existing building

A retrofit raises questions a new building does not: the floor that is already there, the height you have, the power the building can spare, where water can drain and how panels get in. The site assessment answers them one by one.

What you are handed at the end

For a system that uses a scheduled refrigerant, the refrigerant handling code of practice sets out what comes with it when it is finished.

  • The installer provides the operation and maintenance instructions with the completed system.
  • An identification plate goes on or near the system at installation. It shows who installed or made it, the model, the year, and the refrigerant and how much the system holds.
  • A system holding more than 3 kg of refrigerant is supplied with a logbook for its maintenance and repairs.

Keep all three with the room. To put the room on a service schedule from the start, see the commercial refrigeration maintenance page.

Towns ABL covers

ABL is based in Bairnsdale and works across Gippsland, from Morwell to the New South Wales border. A town with a link has its own page.

If your town is not here, call and ask. See also service areas.

Sources (19)

Planning a coolroom or freezer room?

Send ABL your project brief with an enquiry, or call and talk it through.