Converting a storeroom into a coolroom: what to check before you start
Whether an existing room can become cold storage: walls, space left, floor, damp, power, drainage, permits and second-hand panels, with a feasibility sheet.
Last updated
The usual way to convert a storeroom into a coolroom is to build an insulated panel room inside it, not to line the walls you already have. A cold room needs a skin that keeps water vapour out on its warm side. Steel-faced panels give that, and ordinary walls and ceilings are not built to. So the real questions are how much room is left once the panels, floor and plant are in, whether damp, the floor and the building allow it, and whether power and a drain are close. Record what you can see, and leave the structural and refrigeration decisions to the site assessment.
How to use this guide
Step 1: Look at the room
Its walls, floor, height, damp, power and drain, from the outside.
Go to ObservationsStep 2: Fill in the feasibility sheet
What you found, and what is still for us to decide.
Go to the recordStep 3: Call
Bring the sheet to the site assessment, or read it out when you call.
Call (03) 5153 2650
Why the walls you have are not enough
Warm air carries water vapour, and it travels towards the cold. A cold room's insulation has to be sealed against vapour on its outside, warm face. If vapour gets past that seal, it freezes inside the walls of a room below zero, and runs as condensation in a warmer one. Steel skins on insulated panels stop vapour. Ordinary walls and ceilings are not built to.
- Every hole matters. Refrigerant pipes, cables, light fittings, supports and sprinkler pipes all pass through the insulation, and each needs sealing. Agree before work starts who seals what, because other trades often make those holes.
- Small gaps cost a lot. Even small gaps between panels, or around pipes entering a wall, let warm, moist air into the room.
- Surfaces have to suit food. Plasterboard and other absorbent wall surfaces are generally not suitable where they get splashed or touch food, unless covered with tiles or another impervious material. A coolroom floor has to be easy to clean, and coving suits a floor that is hosed.
- An old floor may need work. Unsealed timber and other absorbent floors are generally considered unsuitable for food premises. Safe Food Australia's example is a storeroom with an unsealed timber floor that was approved, in writing, for packaged, non-perishable food only. Under a coolroom, expect the floor to need sealing, covering or a panel floor, and ask the council or Safe Food Victoria, whichever registers or licenses your business.
Water is the enemy of the panels too. Water has to drain freely away from the panels, most of all at their base, and water that gets into a panel and freezes makes it bulge. A storeroom that is damp, leaks or is hosed out needs that dealt with in the design. A low masonry kerb under the panel walls is the recommended way: it lets water drain away and protects the base of the wall.
How much space is left once the panels are in?
Every wall panel comes off the inside of the room, so each dimension loses two panel thicknesses. How thick the panels are depends on the temperature and on the insulation inside them. The federal government's energy guide for refrigeration (opens in a new tab) recommends at least R4.5 for a coolroom and at least R6 for a freezer. A polyisocyanurate (PIR) core reaches R4.5 at about 100 mm. Expanded polystyrene (EPS) needs more than 140 mm, which in the usual panel thicknesses means a 200 mm panel.
| Wall panels | Inside size left | Floor area left |
|---|---|---|
| None (the room as it is) | 3.0 m by 2.5 m | 7.5 square metres |
| 100 mm panels | 2.8 m by 2.3 m | About 6.4 square metres, around 14% less |
| 200 mm panels | 2.6 m by 2.1 m | About 5.5 square metres, around 27% less |
The real figures for your room are set at the site assessment, and any gap left between the panels and the old walls comes off too. Height goes the same way:
- The ceiling panel comes off the height, and so does an insulated floor if the room has one.
- The evaporator hangs inside the room, not over the door. Stock is kept clear below it and is not stacked in front of its fans, so the space under it is not full storage height.
- The doorway in the panel wall has to give a clear opening at least 600 mm wide and 1.5 m high, under the National Construction Code 2025 (opens in a new tab), clause G1D3. The existing doorway has to fit the panel door frame as well.
- Shelving and gaps take more again. A room cannot be packed to its walls, because cold air has to move around the stock.
If you are still weighing a room against cabinets, see the guide to a coolroom or commercial fridges.
The floor, and a room below freezing
- A coolroom can usually sit on a level existing floor. Insulating the floor as well, to about R4.9 or better, cuts the heat that comes up through it. Whether that is worth it in your room is part of the design.
- A freezer room needs an insulated floor, and often heating under that insulation. Below a freezer the ground freezes, the moisture in it expands, and the floor can crack and lift.
- A freezer room also needs a pressure relief valve in its wall.
- A ramp is common at a freezer door. Many coolrooms need none.
A freezer on an upper floor or a suspended floor raises its own questions, and the structure of the floor is for an engineer. Tell us where the room is.
Drainage, power and where the plant goes
| Service | What it needs | What to note now |
|---|---|---|
| Drain | Water from the evaporator runs through a trap, with a steady fall, to an open drain, and is not joined straight to the sewer. The trap sits in a warm space, outside a freezer. Local plumbing rules govern. | Where the nearest floor waste or drain is, and how far. |
| Power | Fixed wiring is work for a licensed electrician. Work on the main switchboard is prescribed electrical work, which Energy Safe Victoria (opens in a new tab) says needs an independent inspection before the Certificate of Electrical Safety is issued. | Where the switchboard is, single-phase or three-phase if you know, and its age. |
| The plant | Somewhere with free air for its heat, room to service it, and a mounting strong enough to carry it without passing vibration and noise into the building. | Possible spots: an outside wall, the yard or the roof, and whether neighbours are close. |
| Gas cylinders | If the room will store beverage gas cylinders, South Gippsland Shire Council's fit-out guide (opens in a new tab) says a gas monitoring and alarm system should be installed. | Whether gas cylinders will be kept in the room. |
At the site assessment we look at the structure, how much the floor can carry, whether the electrical supply is enough and where water can drain. Plant on a roof or an outside wall can add loads the building was not designed for, which is a question for an engineer and the building surveyor. For where the plant should go, see the guide to an indoor or outdoor coolroom.
Permits, asbestos and older buildings
Ask a private building surveyor whether the conversion needs a building permit before any work starts. The Building Act 1993 (opens in a new tab) says a person must not carry out building work unless a building permit is in force for it, and the Building Regulations 2018 (opens in a new tab) list exemptions in Schedule 3. South Gippsland Shire Council's fit-out guide (opens in a new tab) notes that a building permit is required to install a walk-in cool room or freezer. In East Gippsland, building permits come from private building surveyors, not the council (opens in a new tab).
For a food business, East Gippsland Shire Council recommends submitting floor plans for assessment (opens in a new tab) before any works at a proposed or existing food premises. Safe Food Victoria (opens in a new tab) licenses dairy, meat and seafood businesses, so those businesses ask it instead.
| Check | What the rules say | Who to ask |
|---|---|---|
| Asbestos | If a building was built or renovated before 1990, the Victorian Asbestos Hub (opens in a new tab) says to assume asbestos is present until proven otherwise, and not to start work until you know. The owner of a commercial building must keep an asbestos register (opens in a new tab), give it to anyone doing work that may involve exposure, and make sure asbestos is removed before refurbishment. | The building owner for the register. If you lease, WorkSafe Victoria (opens in a new tab) says a tenant running a business is generally not the person with management or control of the building. |
| Victorian Heritage Register | Altering a registered place needs a permit, or a determination that none is needed, under the Heritage Act 2017 (opens in a new tab). The alterations exemption in the Building Regulations does not apply to it. | Heritage Victoria. |
| Heritage Overlay | A planning permit is usually needed for external works, such as plant on a wall or the roof. Internal works usually need none, unless the overlay applies internal controls, as Wellington Shire Council (opens in a new tab) explains. | Your council's planning department. A property planning report or myLot (opens in a new tab) shows what applies to the property. |
| Essential safety measures | The alterations exemption in the Building Regulations does not cover work that affects an essential safety measure, such as an exit, a sprinkler or a detector. | The building surveyor. |
Expanding cold storage while the business keeps trading
There are three usual ways to stage the work. Which one fits depends on the space you have, how much stock you carry and when the business is quietest.
| Way to stage it | What it needs | How often the stock moves |
|---|---|---|
| Build the new room beside the old storage, then swap over | Space for the new room while the old storage keeps running. The old storage carries the stock until the new room is running at temperature. | Once. |
| Hire a coolroom for the gap | A level spot near the work, a power point within reach and a way in for the delivery vehicle. ABL hires out coolrooms, and whether one is free depends on the dates, so ask early. The coolroom hire page has the details. | Twice: out to the hire room, and back. |
| Work in a quiet season or while the business is closed | A period when less stock is held, so what is left fits in the storage that is still running. | Once, if any is left to move. |
Whichever way you stage it:
- Food stays under temperature control throughout. Potentially hazardous chilled food is kept at 5°C or below, unless the business can show another temperature is safe, and frozen food stays frozen. Plan where it goes before the room is cleared.
- Dust and fumes. The food premises standard asks premises to keep out dirt, dust, fumes and smoke as far as practicable. Building work brings dust and fumes, so plan which work happens when, and where dust cannot be kept out, cover the food.
- Asbestos comes first. Where the register shows asbestos in the way of the work, it is dealt with before refurbishment starts, and staff are consulted.
- Plans before works. The council's plan assessment comes before the builders, not after.
For a table of where cold storage gaps come during a project, and how to bridge them, see the guide to installing a coolroom in leased premises.
Can second-hand coolroom panels be reused?
Sometimes, and it is worth checking each of these before you buy. If they are your own panels coming from another site, see the guide to planning a modular coolroom relocation.
| Check | Why it matters |
|---|---|
| The core | Cores behave very differently in a fire. Expanded polystyrene melts and gives off flammable gas. PIR is combustible but can char rather than melt. Ask your insurer about the core before you buy, and keep any labels or paperwork, because the building surveyor may ask what the panels are. |
| Thickness for the new use | Older kit rooms can be thinner than today's recommendation of at least R6 for a freezer. Panels from a coolroom may not suit a freezer. |
| Bulges, dents and punctures | A bulge can mean water has got into the panel through a poor joint, a gap at the base or a puncture. Panels that came from a freezer are the ones to look at hardest. |
| Exposed core | Damage that exposes a combustible core should be repaired or sealed. |
| How they have been stored | Panels are kept dry and covered, and stacked so water drains off them. A stack left out in a paddock is a warning sign. |
| The joints | Each maker joins panels its own way, and joints must fit snugly to keep moisture out. Panels from different makers or different rooms may not join well. |
| Warranty | Ask the seller, and the maker, what warranty if any applies to reused panels. |
What you can record, and what the assessment decides
| Area | You record | Decided at the assessment, by |
|---|---|---|
| Fabric | What the walls, ceiling and floor are made of, and when the building was built or last renovated. | Whether the room suits a panel room inside it: us. Asbestos: the building owner's register. |
| Usable size | Inside length, width and height, the lowest point of the ceiling and what hangs below it. | The final inside size after panels, floor and plant: us. |
| Temperature | Chilled, frozen or both. | Panel core and thickness, floor insulation and heating: us, with an engineer for a freezer slab. |
| Moisture | Damp, leaks, staining or mould, whether the floor is hosed, and wet or steamy rooms next door. | Drainage away from the panel base and sealing of every hole: us. |
| Power | Where the switchboard is, and single-phase or three-phase. | What supply the plant needs and the work to get it: a licensed electrician. |
| Drain | The nearest floor waste or drain, and how far it is. | The route for the evaporator's water: us, with a plumber where plumbing work is involved. |
| Plant | Possible spots for it, and how close the neighbours are. | Mounting, loads, airflow and noise: us, with an engineer and the building surveyor. |
| Permits and heritage | Whether the building is on the Heritage Register or in a Heritage Overlay. | Building permit: a private building surveyor. Planning or heritage permit: the council and Heritage Victoria. |
Storeroom feasibility sheet
Bringing ABL in
ABL fits coolrooms and freezer rooms into existing buildings. Send the feasibility sheet with your enquiry, or have it in front of you when you call, and photos of the room help. The coolroom installation page explains the stages of a build and what drives the cost. If you lease the building, see the guide to installing a coolroom in leased premises first.
Sources (33)
Checked on 19 November 2026
- AIRAH: Skills Workshop 131, insulated enclosures for coldrooms, May 2020 (opens in a new tab)
- AIRAH: walk-in cool room and freezer research, findings and recommendations, September 2018 (opens in a new tab)
- Australian Government, energy.gov.au: refrigeration guide for businesses (opens in a new tab)
- BlueScope: technical bulletin 31, COLORBOND Intramax steel for coolroom panels, December 2020 (opens in a new tab)
- Food Standards Australia New Zealand: Safe Food Australia, chapter 3.2.3, food premises and equipment (opens in a new tab)
- Food Standards Australia New Zealand: Safe Food Australia, chapter 3.2.2 (opens in a new tab)
- Australian Building Codes Board: National Construction Code 2025, Volume One, Part G1, clause G1D3 (opens in a new tab)
- Heatcraft: installation and operations manual for unit coolers (opens in a new tab)
- Heatcraft: installation and operations manual for condensing units, September 2026 (opens in a new tab)
- KPS Global: how to install a walk-in cooler or freezer (opens in a new tab)
- Danfoss (DEVI): cold store protection systems, application manual (opens in a new tab)
- Energy Safe Victoria: Restricted Electrical Worker licence, reviewed 1 July 2026 (opens in a new tab)
- Energy Safe Victoria: Certificate of Electrical Safety (opens in a new tab)
- Victorian Legislation: Building Act 1993, authorised version 153 (opens in a new tab)
- Victorian Legislation: Building Regulations 2018, authorised version 032 (opens in a new tab)
- Victorian Legislation: Heritage Act 2017, authorised version 009 (opens in a new tab)
- South Gippsland Shire Council: food business fit out guide, 2024 (opens in a new tab)
- East Gippsland Shire Council: food businesses and stalls (opens in a new tab)
- East Gippsland Shire Council: building permits (opens in a new tab)
- East Gippsland Shire Council: applying for a planning permit (opens in a new tab)
- Wellington Shire Council: heritage and planning permits (opens in a new tab)
- Safe Food Victoria: home page, updated 10 November 2026 (opens in a new tab)
- Victorian Asbestos Hub: builders and trades (opens in a new tab)
- Victorian Asbestos Hub: property owner and manager duties, modified 30 September 2026 (opens in a new tab)
- WorkSafe Victoria: understand and manage asbestos in workplaces, reviewed 9 May 2024 (opens in a new tab)
- Vero Insurance: risk insight, insulated sandwich panels, 19 August 2020 (opens in a new tab)
- Bondor: MetecnoPanel PIR information guide, February 2016 (opens in a new tab)
- Bromic: modular coldroom installation manual, May 2005 (opens in a new tab)
- Kingspan Paroc Panel System: handling instructions for elements (opens in a new tab)
- Australian Building Codes Board: condensation in buildings handbook, June 2023 (opens in a new tab)
- Victorian Asbestos Hub: employers, employees and the self-employed (opens in a new tab)
- Food Standards Australia New Zealand: storing food safely (opens in a new tab)
- ABL Refrigeration: commercial refrigeration services (opens in a new tab) ABL's own page.
Related pages
- Installing a coolroom in leased premises: the permission and project brief
If the building is leased, settle the landlord's side first.
- Coolroom or commercial fridges: choosing storage format and capacity
Whether a room is the right answer at all.
- Indoor or outdoor coolroom: choosing a location
Where the room and its plant should go.