Setting up a commercial air conditioning asset register
How to build an asset register for commercial air conditioning: labels, spaces served, controls, condition, service history and the records to keep.
Last updated
An asset register is one list of every air conditioning unit you are responsible for. Each unit gets a label that ties it to the drawings, controllers, invoices and service reports, and an entry that records what it is, where it is, what it serves, its condition and history, and how much the business depends on it. Start it from the handover folder or a walk around the site, and update it at every service and every change to the building.
How to use this guide
Step 2: Record what matters
Identity, what it serves, condition, history and importance.
Go to What to record
What the register is for
- Maintenance. The register is the list a maintenance agreement covers, so every unit gets serviced and none is forgotten. The guide to commercial maintenance agreements covers what to compare.
- Diagnosis. Up-to-date records of what each unit serves, how it is controlled and what has gone wrong before speed up finding a fault, and show when the same fault keeps coming back.
- Warranty. The records show the unit was installed and maintained the way its warranty terms require.
- Planning. Replacements can be ranked by age, fault history, how much the business depends on each unit, and whether parts are still available. The guide to repairing or replacing a commercial air conditioning system uses those facts.
A new system should arrive with an equipment list, drawings and a handover folder, as the guide to commercial commissioning and handover describes. That folder is where the register starts. For a system that came without one, start with a walk around the site and the nameplates you can reach from the ground. Do not go onto a roof for a nameplate: ask the technician to photograph it at the next service.
One label for each unit, used everywhere
Give every unit a short label and use it everywhere the unit appears: on the unit, beside its controller, on the floor plan, in the point names of the building management system, on invoices, in service reports and in the fault log. When a service report says "AC-07, fault code on the controller" and the invoice says "AC-07 repair", you can follow one unit's history without guessing which one was "the unit in the back office". There is no set scheme, and any code works if everyone uses it the same way. The one below is a suggested way to build it.
- Build the label from where and what. A code that carries the floor and the type, such as L1-AC-03 for the third unit on level 1, lets a new person find the unit. Some large owners tie each code to the room on their drawings and name their photos by the same code.
- Pair the indoor and outdoor parts. Label a split system's outdoor unit to match its indoor unit, for example AC-03 inside and AC-03-O outside.
- Label a VRF system as a system. Give the outdoor units one label and number the indoor units under it, for example VRF-1 and VRF-1-05.
- Match the controllers. Record which zone name on each controller belongs to which label, or rename the zones to match.
- Ask contractors to use your labels on their reports and invoices, and to label new units before handover.
- Keep the history when a unit is replaced. Record the new model and serial number against the same position, with the date, so the record of that position carries on.
What to record for each unit
| Record | What to write | Where it comes from |
|---|---|---|
| Identity | Label, type, brand, model, serial number, capacity, refrigerant and its charge, year installed and installer. | The identification plate, which the refrigerant handling code requires to show the installer or maker, the model, serial number or reference number, the year of manufacture, the refrigerant and its charge. The handover equipment list and invoices. |
| Location | Where the indoor and outdoor parts are, and how to reach each. | A walk around the site and the drawings. |
| What it serves | The rooms or zones it heats and cools. | Standing in the rooms while it runs, and the handover zone list. |
| Controls | Which controller runs it, the zone name on that controller, any link to the building management system and its point names, and the schedule. | The controllers and the building management system. |
| Condition | A rating, the date, who judged it, and photos named by the label. | Service reports and inspections. |
| Service history | Each visit: date, contractor, what was done, and the report. | Service reports and invoices. |
| Open issues | Anything unresolved, who owns it, and by when. | Reports and your own notes. |
| Importance | What happens to the business if the unit fails. | Your judgement. |
| Replacement access | How the unit would come out and a new one go in: crane, roof access, ceiling, pipe routes and power. | A technician's view, and the guide to laying out outdoor units on a roof. |
| Paperwork | Warranty start date, terms and conditions; the Certificate of Electrical Safety and the plumbing compliance certificate; the refrigerant logbook. | The handover folder. |
| Record owner | The person who keeps this entry current. | You. |
A sample register
Three entries from an example shop, showing how the label ties each unit to what it serves and what controls it. Importance uses the five-step scale in the next section. A real register adds the condition, history, open issues, access and record owner from the table above.
| Label | Unit and location | Serves | Controlled by | Importance (1 to 5) |
|---|---|---|---|---|
| AC-01 | Ducted indoor unit in the ceiling over the corridor. Outdoor unit AC-01-O on the east roof. Model and serial number from both nameplates. | Shop floor and fitting rooms | Wall controller "Shop" by the counter. Building management system: on, off and fault. | 4: stops part of the business, the trading floor |
| AC-02 | Wall split in the office. Outdoor unit AC-02-O on the rear wall. Model and serial number from both nameplates. | Office | Handheld remote. No building management link. | 2: staff can move |
| AC-03 | Wall split in the comms cupboard. Outdoor unit AC-03-O beside AC-02-O. Model and serial number from both nameplates. | Comms cupboard and server | Its own controller, set to run around the clock. Building management system: high temperature alarm. | 5: the network stops if it fails |
Condition, importance and replacement
Rate condition and importance on simple scales, so units can be compared across a site, or across several sites. There is no required scale. The five-step one below is a suggested way to do it, adapted from one large owner's published asset standard, and what matters most is that everyone who rates a unit uses the same words. Importance weighs the effect of a failure on the business, on safety and on stock, whether the unit is the only thing serving its space, how hard it is to maintain and how long parts take to arrive.
| Rating | Condition | Importance |
|---|---|---|
| 1 | As new, no defects. | Its failure would barely be noticed. |
| 2 | Minor wear, working well. | Inconvenient, easily worked around. |
| 3 | Wear and some faults, still working. | Disrupts an area until it is fixed. |
| 4 | Poor, with repeated faults. | Stops part of the business, or puts stock or equipment at risk. |
| 5 | Failed, or unfit for use. | Stops the business, or creates a safety risk. |
Read the two together. A unit in poor condition that matters little can wait for its turn. A critical unit in fair condition may justify spare parts on hand, a standby unit, or an earlier replacement. Replacement access belongs in the same entry, because a unit that needs a crane, a road closure or a ceiling opened costs more to replace than one beside a door, and that cost belongs in the plan.
Records the law and the warranty terms ask for
- Essential safety measures. Some air handling systems can be essential safety measures: air handling systems used for smoke hazard management, and mechanical ventilation that incorporates a cooling tower or a hot or warm water system. For a building built or altered since 1 July 1994, the occupancy permit or the certificate of final inspection lists them. For an older building, ask a building surveyor which apply. The Building and Plumbing Commission (opens in a new tab) says the owner of a building other than a house must maintain them, have an annual essential safety measures report prepared, and keep records of maintenance checks and repair work for inspection. Regulation 225 of the Building Regulations 2018 (opens in a new tab) asks for the annual reports of the last 10 years, the maintenance schedules and the records of all inspections, testing and maintenance, including repairs, to be available at the building within 24 hours after a request by the municipal building surveyor or the chief officer.
- The refrigerant logbook. For a system with a refrigerant charge over 3 kg, the refrigerant handling code of practice (opens in a new tab) says the maker or installer must supply a logbook with the system documents. It records maintenance and repairs, refrigerant added or taken out, component changes and the results of periodic tests. Keep it with the unit's entry and ask each technician to fill it in.
- Cooling towers. The person who owns, manages or controls a cooling tower system must keep written records of all maintenance and corrective work from the last 12 months, and the laboratory reports for the required tests, and produce them to an authorised officer on request, under regulation 79 of the Public Health and Wellbeing Regulations 2019 (opens in a new tab). The guide to central air conditioning or local systems covers the other cooling tower duties.
- Electrical and plumbing paperwork. The Certificate of Electrical Safety and the plumbing compliance certificate for each installation.
Warranty terms differ from one maker to the next, so read the terms for each unit and keep what they turn on:
| What the terms turn on | What to keep |
|---|---|
| When the warranty starts: purchase, installation or commissioning, depending on the maker. | The purchase invoice, and the installation and commissioning dates. |
| Who installed it: several makers exclude a unit not installed by a licensed or qualified installer, and some cards ask for the installer's licence number. | The installer's name, licence number and invoice. |
| Maintenance: the owner is to maintain the unit as its instructions set out. Some makers set a frequency, and one asks for servicing at least every three months for commercial use. | Dated service reports that say what was done. |
| Who repairs it: some warranties exclude repairs by anyone other than the maker's own service agents. | Who did each repair. |
| Claims and registration: some makers want notice within 30 days of a defect, and one wants the warranty registered within 14 days. | The date each fault was first noticed, and the registration confirmation. |
| A new owner: some warranties do not transfer to a new owner, and others transfer on written notice. | Changes of ownership, and any notice sent. |
| Moving the unit: several makers exclude a unit reinstalled away from its original location. | Any relocation, with its date. |
| Server rooms: makers that mention them reduce or exclude the cover. | What the unit serves. |
To claim, makers mostly ask for proof of purchase or installation, and they exclude failures caused by missed maintenance. Dated service reports are what show the maintenance was done.
Buying a business or taking over premises
Before you take responsibility for a building's air conditioning, find out what you are taking on. Old, poorly kept equipment can mean money spent soon after you take over. Ask the seller or the landlord for:
- the asset register, or a list of every unit with its age
- service reports and invoices for the last few years, and any maintenance agreement, with whether it can be transferred
- the faults that keep coming back, and anything still open
- the warranties still running, their start dates, and whether they transfer to you
- the handover documents, the Certificate of Electrical Safety and plumbing compliance certificate, and the refrigerant logbooks
- the essential safety measures records, if the building has them
Who has to maintain the plant depends on the lease: the guide to central air conditioning or local systems sets out the retail lease rule and how to tell whether yours is a retail premises lease. For a retail premises lease, the disclosure statement (opens in a new tab) asks the landlord to list the plant it provides, air conditioning included, to set out air conditioning maintenance and operating costs, and whether existing plant is in good working order. The Victorian Small Business Commission (opens in a new tab) suggests asking for the condition report and taking photos before you take possession. Photograph every unit and every nameplate you can reach from the ground while you are at it: those photos start your register.
When the operator changes
A new facilities manager, a new maintenance contractor or a new business in the same premises is where records go missing. Hand over in one sitting, with both people present:
- the register and the files behind it
- the maintenance schedule, and when each visit is next due
- the open issues, each with a name against it
- the refrigerant logbooks and the warranty documents, with any notices due
- access to the controllers and the building management system, and the keys to the plant
- the contractors' contacts, and what each is engaged to do
Change the record owner on every entry on the day, so nothing is left with a person who has gone.
After a refurbishment or fitout
A fitout can change what a unit serves even when the unit does not move. Afterwards:
- get the as-installed drawings and the new equipment list from the contractor, and enter new units, with labels, before they go into service
- walk the zones again, and update what each unit serves and the zone names on its controller wherever the rooms changed
- mark removed units as removed, with the date, rather than deleting them, so their history stays
- record any change of refrigerant, which the code requires the technician to label on the system
- note any unit moved to a new position, with the date, and check what that means for its warranty
- ask a building surveyor whether the work affected any essential safety measure
The guide to air conditioning checks before a commercial fitout covers what to sort out before the work starts.
Tracking repeat faults across several sites
A shared fault log shows patterns one site on its own cannot. Log every fault against the unit's label, in the same columns at every site:
| Column | What to write |
|---|---|
| When | The date and time it was noticed. |
| Where | The site and the unit's label. |
| What | What was noticed, and any code on the controller. |
| Conditions | The weather and how busy the space was. |
| Done | What was done, by whom, and the report. |
| Cause | The cause the technician found. |
| Came back | Whether the fault returned, and when. |
Review the log every few months. Look for the same fault on the same model, on units of the same age, at the same time of year, or after the same kind of work. Treat a pattern as a question, not an answer: the same code at three sites can have three different causes, so have each one diagnosed. When a cause is found, check the similar units at the other sites, and tell every site what was learned.
Asset register entry
Who to call
ABL installs, replaces and maintains air conditioning for businesses in Bairnsdale and East Gippsland, and its commercial work includes scheduled maintenance programs. Our commercial air conditioning page covers the service, and the enquiry form is on our air conditioning services page. Send your register or equipment list with the enquiry.
Sources (28)
- ABL Refrigeration: air conditioning services (opens in a new tab) ABL's own page. Checked on 20 November 2026.
- Hong Kong Electrical and Mechanical Services Department: HVAC operation and maintenance best practice, key model framework, revised 6 June 2023 (opens in a new tab) Checked on 20 November 2026.
- US Department of Energy, Federal Energy Management Program: O&M best practices, chapter 5, maintenance programs (opens in a new tab) Checked on 20 November 2026.
- US Department of Energy, Federal Energy Management Program: O&M best practices, chapter 4, maintenance management systems (opens in a new tab) Checked on 20 November 2026.
- US Department of Energy, Federal Energy Management Program: O&M best practices, chapter 11, ten steps (opens in a new tab) Checked on 20 November 2026.
- University of Sydney: asset identification and labelling standard, version 4.0 (opens in a new tab) Checked on 20 November 2026.
- Better Buildings Partnership: guidance note 2.1, an asset register, updated 21 February 2022 (opens in a new tab) Checked on 20 November 2026.
- NSW Government: I am your optimisation guide, heating, ventilation and air conditioning systems, 2015 (opens in a new tab) Checked on 20 November 2026.
- UNSW and the Australian Government: best available HVAC&R retrofit technologies guide for commercial buildings, 2022 (opens in a new tab) Checked on 20 November 2026.
- Government of Western Australia: technical guideline TG009, commissioning and handover, version 2.0 (opens in a new tab) Checked on 20 November 2026.
- Australia and New Zealand refrigerant handling code of practice, part 2, 2025 edition (opens in a new tab) Checked on 20 November 2026.
- Building and Plumbing Commission: essential safety measures (opens in a new tab) Checked on 20 November 2026.
- Building Regulations 2018 (Victoria), authorised version 032, Part 15 and Schedule 8 (opens in a new tab) Checked on 20 November 2026.
- Public Health and Wellbeing Regulations 2019 (Victoria), authorised version 030, regulation 79 (opens in a new tab) Checked on 20 November 2026.
- Energy Safe Victoria: Certificate of Electrical Safety (opens in a new tab) Checked on 17 November 2026.
- Building Act 1993 (Victoria), version of 13 November 2026, sections 221ZH and 221ZL (opens in a new tab) Checked on 17 November 2026.
- Daikin Australia: manufacturer's warranty card (opens in a new tab) Checked on 20 November 2026.
- Mitsubishi Electric Australia: air conditioning warranty card, 2025 (opens in a new tab) Checked on 20 November 2026.
- Mitsubishi Electric Australia: warranty, industry and professional (opens in a new tab) Checked on 20 November 2026.
- ActronAir: warranty terms, document 892A version 18, July 2025 (opens in a new tab) Checked on 20 November 2026.
- Temperzone Australia: warranty document, updated 17 November 2026 (opens in a new tab) Checked on 20 November 2026.
- Toshiba Australia (AHIC): express warranty certificate, 1 August 2023 (opens in a new tab) Checked on 20 November 2026.
- LG Australia: warranty (opens in a new tab) Checked on 20 November 2026.
- Samsung Australia: air conditioning warranty card (opens in a new tab) Checked on 20 November 2026.
- business.gov.au: buy an existing business (opens in a new tab) Checked on 20 November 2026.
- Business Queensland: due diligence when buying a business, updated 10 October 2022 (opens in a new tab) Checked on 20 November 2026.
- Retail Leases Regulations 2023 (Victoria), Schedule 1, disclosure statement (opens in a new tab) Checked on 20 November 2026.
- Victorian Small Business Commission: repairs and maintenance under a retail lease (opens in a new tab) Checked on 20 November 2026.
Related pages
- Commercial air conditioning in Bairnsdale and Gippsland
Scheduled maintenance programs for businesses.
- Commercial HVAC commissioning and handover: what an owner should receive
The documents a new system should arrive with.
- Commercial air conditioning maintenance agreements: questions to ask before you sign
How to compare maintenance proposals for the units on your register.
Setting up records for your air conditioning?
Send ABL your register or equipment list with an enquiry, or call to book a service.
Filled in the record? Copy or print it first: it is not sent with a call or an enquiry.
