Air conditioning checks before a commercial fitout or change of use
What a fitout, new partitions or a change of use does to commercial air conditioning, the six questions to ask of each change, and a change register.
Last updated
Before a fitout or refurbishment changes a room, check what the change does to the air conditioning: the heat each room has to deal with, where air is supplied and returned, which controller runs which room, how each room gets outside air, and whether the equipment can still be reached for servicing. A system that was right for the old layout can be wrong for the new one. The change register in this guide maps each change to those questions, so the air conditioning is assessed before the walls go up, not after people start complaining.
How to use this guide
Step 1: Draw
Mark up a before and after plan of the rooms and the air conditioning.
Go to Before and after planStep 2: Register
List each change and the questions it raises in the change register.
Go to the recordStep 3: Ask
Send the plans and the register with an enquiry, or call before the layout is final.
Call (03) 5153 2650
Why does a fitout affect the air conditioning?
An air conditioning system is designed around a layout: the size of each room, the number of people in it, the equipment that gives off heat, and where the walls and ceilings are. Change any of those and the system is working to a design that no longer matches the building. The result is the complaint that follows many fitouts: one room too cold, the next too warm, and a system that does not settle.
Every change to a room raises the same six questions.
| Question | What it asks | What goes wrong if nobody asks |
|---|---|---|
| Load | How much heat the room now has to deal with: people, computers, appliances, lighting and sun through glass. | A room that holds more people or equipment than it was designed for runs warm, however low the setting. |
| Distribution | Whether the room has an outlet that supplies air, and a path for that air to get back to the unit. | A new room with no outlet gets no conditioning. A room with an outlet and no return path gets little once the door is shut. |
| Controls | Which controller and which temperature sensor run the room, and what else they run. | A sensor left in one room sets the temperature of others it cannot feel. |
| Ventilation | How outside air gets into the room. Heating and cooling a room is not the same as ventilating it. | A closed-in room with no window that opens and no supply of outside air turns stuffy. |
| Access | Whether the indoor units, filters, drains, dampers and outdoor plant can still be reached for servicing. | A unit boxed in behind a new wall or above a fixed ceiling cannot be serviced without damage. |
| Approvals | Whether the landlord, a building surveyor or the council has to agree, and what paperwork follows the work. | Work that has to be redone, or a fitout that cannot be signed off. |
Draw a before and after plan of each room
You do not need drafting software. A copy of the floor plan and a pen will do. The aim is one sheet that shows the air conditioning as it is, and one that shows the layout as it will be.
- Gather what already exists: the floor plan, any air conditioning drawings, the manuals and the service records. If you are a tenant, ask the landlord or building manager for the drawings of the base building system.
- On the "before" plan, write in each room what it is used for, how many people use it, and the hours.
- Mark the air conditioning you can see: indoor units, ceiling outlets, return air grilles, wall controllers and sensors, access hatches, and where the outdoor plant sits.
- Draw the "after" plan: new walls, walls taken out, new ceiling heights, and the new use, people and hours of each room.
- Add what gives off heat or moisture in the new layout: computers and servers, printers, fridges, dishwashers, ovens and urns.
- List every difference between the two plans. Each one is a line in the change register.
Take both plans to whoever will assess the air conditioning before the layout is final. Moving a wall half a metre on paper, so that an outlet and a return grille stay in the same room, costs nothing. Moving it after the plasterboard is up does. The guide to planning air conditioning for offices and shared workspaces covers what a comfort brief for a new layout should say.
Common layout changes and what each one needs
These six changes cover most small commercial fitouts. Each one names the questions that matter most for it.
An open office gains private rooms
One zone becomes several enclosed spaces. Each new room needs its own supply outlet and a path for the air to return, such as a return grille or a grille in the door, or it is starved of air once the door closes. The controller for the old open area ends up inside one of the rooms, or outside all of them, and runs spaces it cannot sense. Meeting rooms are the hardest: a room that holds more than about one person for every 10 square metres can need more cooling and more outside air than ordinary office space.
Partitions are removed
Enclosed rooms become one space. Outlets that suited small rooms may now leave the middle of the floor without air, and two or three controllers end up sharing one room. Left as they are, systems that serve the same space can work against each other, one heating while another cools. The usual answer is to regroup the outlets and the controls as one zone and rebalance the airflow.
A warehouse gains an office mezzanine
Treat the new office as its own design problem, not as an extension of the warehouse. It sits high in the building, under the roof, in the hottest part of a shed in summer. It needs its own heating and cooling, sized for its walls, glass and people, and ventilation in its own right. The structure has to carry the indoor unit, and the outdoor unit needs somewhere to stand, a route for its pipes and a drain. A mezzanine is building work, so ask a building surveyor about a permit before anyone orders equipment.
A ceiling is lowered
A new ceiling changes where the air comes out and how anyone reaches the equipment above it. Outlets, return grilles and cassette units have to be brought down to the new ceiling line, and ducts may need extending to reach them. A new solid ceiling can also close off a return path that ran through the old one. Every indoor unit, filter, damper and drain above the new ceiling needs an access hatch beneath it that is big enough to work through. Mark the hatches on the ceiling plan before the ceiling contractor starts.
The use of the premises changes
A shop that becomes a cafe, an office that becomes a clinic or a store that becomes a gym has different people, hours, heat and moisture from the use the system was designed for. Assume nothing carries over. These are the assumptions to have assessed afresh:
- how many people are in each room, and for how long
- the hours the system runs, including evenings and weekends
- the heat and moisture from cooking, appliances, exercise or equipment
- the outside air each use needs, and any exhaust the new use requires
- whether the existing equipment has the capacity, and is in good enough condition, to stay
The building rules change with the use as well. The approvals section of this guide covers them.
A staff room is moved
Check the new room before people move in. It needs a supply outlet and a return path, a controller that senses it, and ventilation. A staff room also makes its own heat and steam, from a fridge, a microwave, a dishwasher and an urn. A storeroom turned into a staff room often has none of these services. And the room that used to be the staff room may now get more air than it needs.
Why does the air conditioning short cycle after a fitout?
Short cycling means the system starts and stops in quick bursts without settling. When it begins after a fitout, the building work is the first place to look. These are the usual causes.
- The system is now too big for what it serves. A unit sized for an open floor that now serves one enclosed room reaches the set temperature in minutes, stops, and starts again. An oversized unit also leaves a room clammy, uses more power and wears faster.
- The sensor is in the wrong place. The controller or its sensor now sits in a different room from the one the unit serves, or in the path of a supply outlet, so it reads a temperature the room does not have.
- The air cannot get back. A new wall or a closed door has cut the return path, or outlets have been shut off or covered.
- Two systems share one space. Units that used to serve separate rooms now work against each other.
Changing the set temperature again and again does not cure any of these, and it hides the cause. Write down which unit does it, how long it runs and how long it rests, and what changed in the fitout. Then have the system assessed against the new layout. The guide to an air conditioner that starts then stops covers the other causes of short cycling and what to log.
Can the existing air conditioning be reused?
Often, but not on assumption. Before a fitout budget relies on keeping the existing system, have it assessed against the new layout. A proper assessment:
- works out the heat load of each room as it will be used, and compares it with what the existing equipment can deliver
- measures the air the system delivers now, before any work starts, so there is a baseline to work from
- looks at the condition and age of the equipment, and whether parts are still available
- sets out what has to change: outlets moved or added, return paths, controllers and sensors, and zones regrouped
- ends with the airflow rebalanced to the new layout, and the measured results written down
Airflow is the step most often skipped. Once a system has been commissioned, its balance is rarely checked again, and a repartitioned floor is one of the standard reasons a system needs rebalancing. If the equipment is old or has a history of faults, weigh that before a new fitout is built around it. The guide to repairing or replacing a commercial air conditioning system covers that decision.
Who does what on a fitout
| Who | Responsible for | Needs from the others |
|---|---|---|
| The business owner or tenant | The brief: what each room is for, how many people use it, the hours, and the equipment going in. Getting the landlord to agree. | Drawings of what exists, and a straight answer on what the existing system can do. |
| The landlord or building manager | Information about the base building system, the conditions for working on it, and approval of changes to it. | The proposed layout, and what the tenant wants changed. |
| The designer, builder or shopfitter | The layout, the walls and ceilings, the program, and coordinating the trades. | The air conditioning assessment, early enough to change the layout. |
| The building surveyor | Whether the work needs a building permit, and what a change of use or a change to the essential safety measures requires. | The plans, and the current and proposed use. |
| The air conditioning contractor | Assessing the system against the new layout, altering it, rebalancing it and recording the result. | The before and after plans, the ceiling plan, and a look at the ceiling space before it is closed in. |
| The electrician | Power to new or relocated units and controls. | The position and the electrical load of each unit. |
| The ceiling and fire services contractors | Access hatches under the equipment, and sprinklers and detectors moved to suit the new walls. | The position of every unit, outlet and hatch. |
Name one person to coordinate. On a small fitout that is usually the builder or the shopfitter, and on a very small one it is you. Air conditioning trouble after a fitout is less often one trade getting its own work wrong than a gap between two trades.
Approvals and paperwork to check
These are the rules in Victoria as at November 2026. A building surveyor is the person to confirm how they apply to your premises.
- Building permit. The Building and Plumbing Commission (opens in a new tab) says all building work requires a building permit unless the regulations exempt it. Ask your council or a building surveyor before work starts.
- Change of use. Under the Building Regulations 2018 (opens in a new tab), the use of a building must not be changed unless the building meets the requirements that apply to the new use, or a building surveyor grants an exemption. The council may also require a planning permit, because planning permits cover how land is used.
- Essential safety measures. Work that alters a building may affect its essential safety measures (opens in a new tab), which can include air handling systems used to manage smoke, and mechanical ventilation that incorporates a cooling tower or a warm water system. A building surveyor can tell you what has to be done.
- Ventilation. The National Construction Code (opens in a new tab) requires any room or space occupied by a person to have natural ventilation, or a mechanical ventilation or air conditioning system that meets the standards the code names. Heating and cooling a room does not by itself ventilate it, so a newly enclosed room needs its ventilation worked out as well. The guide to air conditioning and outdoor air ventilation explains the difference.
- Asbestos. WorkSafe Victoria says asbestos likely to be disturbed must be identified before refurbishment work starts (opens in a new tab). Ask for the asbestos register before any wall or ceiling is cut into.
- Landlord consent. A lease usually sets conditions for work on the base building systems. Get the consent in writing.
- Paperwork at the end. A Certificate of Electrical Safety for the electrical work, which Energy Safe Victoria (opens in a new tab) says is required for all electrical installation work. A compliance certificate from the licensed plumber for refrigerated air conditioning work worth $750 or more, under the Building Act 1993 (opens in a new tab). And a drawing of the air conditioning as altered, with the measured airflows.
Fitout change register
When to bring in the air conditioning contractor
Before the layout is final. An assessment at the sketch stage can move a wall or add an outlet for little cost. The same finding after handover means opening finished ceilings.
ABL installs, repairs and maintains air conditioning for businesses in Bairnsdale and East Gippsland. Send us your before and after plans and the change register, and ask for the system to be assessed against the new layout. Our commercial air conditioning page covers the service, and the enquiry form is on our air conditioning services page. If the assessment points to new equipment, the guides to budgeting for a replacement and replacing air conditioning while the business stays open explain what comes next.
Sources (14)
- NATSPEC: Simple Office Fitout reference specification, April 2025 (opens in a new tab) Checked on 19 November 2026.
- NSW Government: I am your optimisation guide, heating, ventilation and air conditioning systems, 2015 (opens in a new tab) Checked on 19 November 2026.
- CHOICE: what size air conditioner do I need?, updated 4 November 2026 (opens in a new tab) Checked on 19 November 2026.
- CHOICE: how to fix and maintain your air conditioner, updated 26 February 2021 (opens in a new tab) Checked on 19 November 2026.
- Building and Plumbing Commission: when is a building permit required? (opens in a new tab) Checked on 19 November 2026.
- Building Regulations 2018 (Victoria), version of 27 October 2026 (opens in a new tab) Checked on 19 November 2026.
- Building and Plumbing Commission: essential safety measures (opens in a new tab) Checked on 19 November 2026.
- National Construction Code 2025, volume one, part F6: light and ventilation (opens in a new tab) Checked on 19 November 2026.
- WorkSafe Victoria: understand and manage asbestos in workplaces, reviewed 9 May 2024 (opens in a new tab) Checked on 19 November 2026.
- Energy Safe Victoria: Certificate of Electrical Safety (opens in a new tab) Checked on 17 November 2026.
- Building Act 1993 (Victoria), version of 13 November 2026 (opens in a new tab) Checked on 17 November 2026.
- Building and Plumbing Commission: compliance certificates, updated 9 July 2026 (opens in a new tab) Checked on 17 November 2026.
- Plumbing Regulations 2018 (Victoria), version of 1 May 2026 (opens in a new tab) Checked on 17 November 2026.
- ABL Refrigeration: air conditioning services (opens in a new tab) ABL's own page. Checked on 19 November 2026.
Related pages
- Commercial air conditioning: repair or replace decision guide
How to decide whether the existing system is worth building a fitout around.
- Commercial air conditioning replacement budget: what to allow
The cost lines to allow for if the fitout needs new equipment.
- Commercial AC and outdoor-air ventilation are separate duties
Why heating and cooling a room does not ventilate it.