Air conditioning a new house: decisions to make before the plaster goes on
What to decide and rough in for air conditioning before a new house is lined: positions, pipes, drains, power, access, who does what and the handover.
Last updated
Settle the air conditioning while the frame is open. Before the plasterboard goes up, the positions of the indoor and outdoor units, the pipe and drain routes, the power circuits and the openings for access all need to be decided, run where they will be hidden, and recorded. After that, every change means cutting into finished walls and ceilings. Agree who does each part, what is tested and photographed before the linings go on, and what you receive at handover.
How to use this guide
Step 1: Make the plan
Every unit, route, circuit and access opening, room by room.
Go to Room and services planStep 2: Put a name on each job
Builder, installer, electrician or plumber, in writing.
Go to Who does what
When do the decisions have to be made?
Earlier than most people expect. Consumer Affairs Victoria (opens in a new tab) advises getting everything you want into writing and into the plans and specifications before you sign the building contract, because changes can be expensive afterwards and may need the building permit amended. The usual building stages set the rest of the timing:
| Stage | Air conditioning decisions and work |
|---|---|
| Design and contract | The type of system, the rooms it serves, where the units go, the roof space a ducted system needs, and the switchboard capacity. Whether the builder supplies the air conditioning or you engage an installer. |
| Base and frame | Where each outdoor unit will stand, so paths, slabs and fences suit it. Backing in the walls for wall units, framing for access panels and grilles, and space in the roof for a ducted unit. |
| After the frame inspection, before the linings | The rough-in: refrigerant pipes, drains, power circuits and controller cables run through the frame, then tested and recorded. |
| Fixing and completion | Units fitted, connected and commissioned, and the papers handed over. |
The frame stage is when the home's frame is completed and approved by a building surveyor, in Consumer Affairs Victoria's (opens in a new tab) definition. The completion of the framework is one of the mandatory notification stages in the Building Regulations 2018 (opens in a new tab). Under the Building Act 1993 (opens in a new tab) the builder must notify the building surveyor when each stage is complete, and the surveyor must have the work inspected in person. That is as at November 2026.
New homes in Victoria are all-electric from 1 January 2027, under the state government's announcement (opens in a new tab), so heating as well as cooling is part of the electrical design from the start. A reverse cycle system does both.
What goes on the room and services plan?
Mark these on a copy of the floor plan, room by room. It is the drawing the builder, the installer and the electrician all work from.
| Item | What to mark |
|---|---|
| Indoor units | Each position, on a wall or ceiling with backing behind it, with clear air in front and not blowing straight onto a bed or a seat. |
| Outdoor units | Each position, with the clearances the manual asks for, room to service it, and distance from neighbours' bedroom windows. See the guide to choosing an outdoor unit location. |
| Pipe routes | The path of each pair of pipes and its length, kept as short and direct as the house allows and within the model's limits. |
| Drains | Where each drain runs, with a steady fall of about 1 in 100 or a pump, and where it discharges. See the guide to planning the drain. |
| Power and controls | A circuit for each outdoor unit, the isolating switch positions, and a cable to each wall controller. |
| Access openings | Each access panel for a concealed unit, at the size its manual gives, and the return air grille and filter where they can be reached. |
| Ducted systems | The unit's place in the roof, each outlet, the return grille and the route for every duct, with the roof hatch big enough to get the unit in and out. |
Noise is part of the plan. On a new estate the neighbour's bedroom can be a few metres away, and EPA Victoria's residential noise rules (opens in a new tab) set the hours when air conditioner noise that can be heard in a neighbour's home is unreasonable. The guide to choosing a quiet air conditioner for a bedroom has the times. That is as at November 2026.
For a concealed unit, the space it needs and the access it needs later are covered in AC options when ceiling space is tight and bulkhead or ducted.
Who does each part of the rough-in?
Most rough-in problems come from a job that everyone thought someone else was doing. Put a name against each of these, in writing, before the work starts:
| Task | Usually done by | What to agree |
|---|---|---|
| Refrigerant pipes, and later the connection and commissioning | A licensed air conditioning installer. | Who runs the pipes, who connects them later, and that both are licensed for it. |
| Power circuits, isolating switches, the cable between each indoor and outdoor unit, and controller cables | A licensed electrician. | Whose electrician, and where every circuit and switch goes. |
| Drains to a waste pipe or stormwater | A plumber licensed for sanitary work where the drain joins a waste pipe. The installer where it discharges outside. | Where each drain ends and who connects it. |
| Backing, framing for access panels, bulkheads and the roof hatch | The builder. | The sizes from the manual for each unit, given to the builder before framing. |
| Holes through cladding, roof and fire or acoustic walls, and sealing them | The builder or the installer. | Who makes each hole and who seals it, so none is left open behind a lining. |
| The frame inspection | The building surveyor, notified by the builder. | When it is, so the rough-in follows it. |
| Photos and the updated plan | The installer, or you. | Who keeps the record of where everything was run. |
Under the Plumbing Regulations 2018 (opens in a new tab), refrigerated air conditioning work is a class of plumbing work in Victoria, and handling refrigerant needs a refrigerant handling licence (opens in a new tab). Fixed electrical work is for a licensed electrician. The guide to the electrical work in a quote covers the circuit and the switchboard.
What should be checked before the walls close?
Once the plasterboard is on, nobody can see the rough-in again without cutting it open. Before it goes on, check and record these:
- Pipe ends are sealed. Open pipes let in dirt and moisture, so every end stays capped until the units are connected.
- Pipes are insulated. Each refrigerant pipe is insulated separately, and the drain is insulated where it runs through the house.
- The pipe runs have been pressure tested, and the result is written down. Ask how the installer tests and records it.
- The drains fall the whole way, or reach the pump position, and have been tested with water before the ceiling closes.
- Circuits, isolating switch positions, the cable between the units and controller cables are in place and labelled.
- Backing and access framing are where the plan shows them, at the sizes the manuals give.
- Every hole through the outside of the house is sealed against weather.
- Photos are taken of every run, with a tape measure or a fixed point in the shot, and the plan is updated to match.
The refrigerant handling code of practice (opens in a new tab) requires all sections of a system built on site to be leak tested before the system is charged with refrigerant, and pipework to be protected from dirt and moisture during construction. Scheduled refrigerant must not be used for the test. Write down anything still undecided, with a date and a name against it, so it is not quietly left for the linings to hide.
What is due at handover?
When the units are fitted they are commissioned and tested, and you are shown how to use them. Two certificates follow the work. Energy Safe Victoria (opens in a new tab) says a Certificate of Electrical Safety for work such as air conditioning is to be given to you within 30 days. For plumbing work with a total value of $750 or more, the Building Act 1993 (opens in a new tab) requires a plumbing compliance certificate (opens in a new tab), given to you within five days of finishing. That is as at November 2026.
Ask for the room and services plan and the rough-in photos as well, because they are the only record of what is behind the walls. The guide to commissioning and handover lists everything to receive and check.
Pre-plaster coordination checklist
Fill in the names first, then tick the rest off before the linings go on. Send the plan with an enquiry when you want a quote: our air conditioning page explains how to ask, and our ducted air conditioning and split system installation pages cover each kind of system.
Other questions about a new build
Should I let the builder supply the air conditioning, or use my own installer?
Either can work. If the builder supplies it, check what the contract allows for it: Consumer Affairs Victoria (opens in a new tab) gives air conditioning as an example of a provisional sum, which is an estimate, not a fixed price. If you use your own installer, the builder has to know who is coming, when, and what the rough-in needs from the frame.
Can the pipes be roughed in now and the units fitted later?
Yes, and that is the usual way. The pipes and drains go in before the linings, and the units are fitted near the end, once the dusty work is done.
What if the plan changes after the walls are up?
Then the change means cutting and patching, and it may need a variation to the building contract. The guide to planning air conditioning through a renovation covers changes during building work.
Sources (19)
- Consumer Affairs Victoria: building plans and permits, updated 8 July 2025 (opens in a new tab) Checked on 20 November 2026.
- Consumer Affairs Victoria: building definitions (opens in a new tab) Checked on 20 November 2026.
- Building Regulations 2018 (Victoria), version 032, regulation 167 (opens in a new tab) Checked on 20 November 2026.
- Building Act 1993 (Victoria), version 153, sections 33 and 34 (opens in a new tab) Checked on 20 November 2026.
- Premier of Victoria: securing Victoria's gas supply while slashing energy bills, 24 June 2025 (opens in a new tab) Checked on 17 November 2026.
- EPA Victoria: residential noise, updated 4 November 2026 (opens in a new tab) Checked on 20 November 2026.
- Australia and New Zealand refrigerant handling code of practice, part 2, 2025 edition (opens in a new tab) Checked on 20 November 2026.
- Australian Refrigeration Council: frequently asked questions (opens in a new tab) Checked on 17 November 2026.
- Plumbing Regulations 2018 (Victoria), version 010 (opens in a new tab) Checked on 17 November 2026.
- Energy Safe Victoria: Certificates of Electrical Safety for consumers, reviewed 17 September 2026 (opens in a new tab) Checked on 20 November 2026.
- Building Act 1993 (Victoria), version of 13 November 2026 (opens in a new tab) Checked on 17 November 2026.
- Building and Plumbing Commission: compliance certificates (opens in a new tab) Checked on 17 November 2026.
- AIRAH: residential air conditioning best practice guide (Victoria), second edition 2026 (opens in a new tab) Checked on 20 November 2026.
- Fujitsu General Australia: installation summary for the KSLAP ducted series, January 2026 (opens in a new tab) Checked on 20 November 2026.
- Fujitsu General Australia: installation manual for ARTH09 to 18 KSLAP slim ducted indoor units (opens in a new tab) Checked on 20 November 2026.
- Fujitsu General Australia: installation manual for ASTG30 CMTA wall mounted units (opens in a new tab) Checked on 20 November 2026.
- Fujitsu General Australia: installation manual for AOTG30 CMTA outdoor units (opens in a new tab) Checked on 20 November 2026.
- Mitsubishi Electric Australia: installation manual for PEAD-M50 to 140JAA ducted indoor units (opens in a new tab) Checked on 20 November 2026.
- ABL Refrigeration: air conditioning services (opens in a new tab) ABL's own page. Checked on 20 November 2026.
Related pages
- Split system installation in Bairnsdale and East Gippsland
What ABL installs, and the quote details to send.
- Air conditioning commissioning and handover: a checklist for the homeowner
What to receive and check when the system is finished.
- Planning the condensate drain for a split system
Where the water goes, and when a pump is needed.