Air conditioning a new house: decisions to make before the plaster goes on

What to decide and rough in for air conditioning before a new house is lined: positions, pipes, drains, power, access, who does what and the handover.

Last updated

Settle the air conditioning while the frame is open. Before the plasterboard goes up, the positions of the indoor and outdoor units, the pipe and drain routes, the power circuits and the openings for access all need to be decided, run where they will be hidden, and recorded. After that, every change means cutting into finished walls and ceilings. Agree who does each part, what is tested and photographed before the linings go on, and what you receive at handover.

How to use this guide

  1. Step 1: Make the plan

    Every unit, route, circuit and access opening, room by room.

    Go to Room and services plan
  2. Step 2: Put a name on each job

    Builder, installer, electrician or plumber, in writing.

    Go to Who does what
  3. Step 3: Use the checklist

    Tick it off before the walls close.

    Go to the record

When do the decisions have to be made?

Earlier than most people expect. Consumer Affairs Victoria (opens in a new tab) advises getting everything you want into writing and into the plans and specifications before you sign the building contract, because changes can be expensive afterwards and may need the building permit amended. The usual building stages set the rest of the timing:

Building stages, and the air conditioning work that belongs to each
StageAir conditioning decisions and work
Design and contractThe type of system, the rooms it serves, where the units go, the roof space a ducted system needs, and the switchboard capacity. Whether the builder supplies the air conditioning or you engage an installer.
Base and frameWhere each outdoor unit will stand, so paths, slabs and fences suit it. Backing in the walls for wall units, framing for access panels and grilles, and space in the roof for a ducted unit.
After the frame inspection, before the liningsThe rough-in: refrigerant pipes, drains, power circuits and controller cables run through the frame, then tested and recorded.
Fixing and completionUnits fitted, connected and commissioned, and the papers handed over.

The frame stage is when the home's frame is completed and approved by a building surveyor, in Consumer Affairs Victoria's (opens in a new tab) definition. The completion of the framework is one of the mandatory notification stages in the Building Regulations 2018 (opens in a new tab). Under the Building Act 1993 (opens in a new tab) the builder must notify the building surveyor when each stage is complete, and the surveyor must have the work inspected in person. That is as at November 2026.

New homes in Victoria are all-electric from 1 January 2027, under the state government's announcement (opens in a new tab), so heating as well as cooling is part of the electrical design from the start. A reverse cycle system does both.

What goes on the room and services plan?

Mark these on a copy of the floor plan, room by room. It is the drawing the builder, the installer and the electrician all work from.

What the room and services plan shows
ItemWhat to mark
Indoor unitsEach position, on a wall or ceiling with backing behind it, with clear air in front and not blowing straight onto a bed or a seat.
Outdoor unitsEach position, with the clearances the manual asks for, room to service it, and distance from neighbours' bedroom windows. See the guide to choosing an outdoor unit location.
Pipe routesThe path of each pair of pipes and its length, kept as short and direct as the house allows and within the model's limits.
DrainsWhere each drain runs, with a steady fall of about 1 in 100 or a pump, and where it discharges. See the guide to planning the drain.
Power and controlsA circuit for each outdoor unit, the isolating switch positions, and a cable to each wall controller.
Access openingsEach access panel for a concealed unit, at the size its manual gives, and the return air grille and filter where they can be reached.
Ducted systemsThe unit's place in the roof, each outlet, the return grille and the route for every duct, with the roof hatch big enough to get the unit in and out.

Noise is part of the plan. On a new estate the neighbour's bedroom can be a few metres away, and EPA Victoria's residential noise rules (opens in a new tab) set the hours when air conditioner noise that can be heard in a neighbour's home is unreasonable. The guide to choosing a quiet air conditioner for a bedroom has the times. That is as at November 2026.

For a concealed unit, the space it needs and the access it needs later are covered in AC options when ceiling space is tight and bulkhead or ducted.

Who does each part of the rough-in?

Most rough-in problems come from a job that everyone thought someone else was doing. Put a name against each of these, in writing, before the work starts:

Rough-in tasks and who usually does them
TaskUsually done byWhat to agree
Refrigerant pipes, and later the connection and commissioningA licensed air conditioning installer.Who runs the pipes, who connects them later, and that both are licensed for it.
Power circuits, isolating switches, the cable between each indoor and outdoor unit, and controller cablesA licensed electrician.Whose electrician, and where every circuit and switch goes.
Drains to a waste pipe or stormwaterA plumber licensed for sanitary work where the drain joins a waste pipe. The installer where it discharges outside.Where each drain ends and who connects it.
Backing, framing for access panels, bulkheads and the roof hatchThe builder.The sizes from the manual for each unit, given to the builder before framing.
Holes through cladding, roof and fire or acoustic walls, and sealing themThe builder or the installer.Who makes each hole and who seals it, so none is left open behind a lining.
The frame inspectionThe building surveyor, notified by the builder.When it is, so the rough-in follows it.
Photos and the updated planThe installer, or you.Who keeps the record of where everything was run.

Under the Plumbing Regulations 2018 (opens in a new tab), refrigerated air conditioning work is a class of plumbing work in Victoria, and handling refrigerant needs a refrigerant handling licence (opens in a new tab). Fixed electrical work is for a licensed electrician. The guide to the electrical work in a quote covers the circuit and the switchboard.

What should be checked before the walls close?

Once the plasterboard is on, nobody can see the rough-in again without cutting it open. Before it goes on, check and record these:

  • Pipe ends are sealed. Open pipes let in dirt and moisture, so every end stays capped until the units are connected.
  • Pipes are insulated. Each refrigerant pipe is insulated separately, and the drain is insulated where it runs through the house.
  • The pipe runs have been pressure tested, and the result is written down. Ask how the installer tests and records it.
  • The drains fall the whole way, or reach the pump position, and have been tested with water before the ceiling closes.
  • Circuits, isolating switch positions, the cable between the units and controller cables are in place and labelled.
  • Backing and access framing are where the plan shows them, at the sizes the manuals give.
  • Every hole through the outside of the house is sealed against weather.
  • Photos are taken of every run, with a tape measure or a fixed point in the shot, and the plan is updated to match.

The refrigerant handling code of practice (opens in a new tab) requires all sections of a system built on site to be leak tested before the system is charged with refrigerant, and pipework to be protected from dirt and moisture during construction. Scheduled refrigerant must not be used for the test. Write down anything still undecided, with a date and a name against it, so it is not quietly left for the linings to hide.

What is due at handover?

When the units are fitted they are commissioned and tested, and you are shown how to use them. Two certificates follow the work. Energy Safe Victoria (opens in a new tab) says a Certificate of Electrical Safety for work such as air conditioning is to be given to you within 30 days. For plumbing work with a total value of $750 or more, the Building Act 1993 (opens in a new tab) requires a plumbing compliance certificate (opens in a new tab), given to you within five days of finishing. That is as at November 2026.

Ask for the room and services plan and the rough-in photos as well, because they are the only record of what is behind the walls. The guide to commissioning and handover lists everything to receive and check.

Pre-plaster coordination checklist

Fill in the names first, then tick the rest off before the linings go on. Send the plan with an enquiry when you want a quote: our air conditioning page explains how to ask, and our ducted air conditioning and split system installation pages cover each kind of system.

Pre-plaster coordination checklist

Fill in who does what, then check each item against the room and services plan before the walls close.

Your answers stay on this open page. They are not saved or sent. Copy or print them before you leave.

The people and the dates

The plan

Unit positions marked and agreed
Backing and access framing in place

Pipes and drains

Pipe ends capped and pipes insulated
Drains
Drains water tested

Power and controls

Circuits and isolating switch positions run
Controller cables run

Records and open items

Photos taken and plan updated

Other questions about a new build

Should I let the builder supply the air conditioning, or use my own installer?

Either can work. If the builder supplies it, check what the contract allows for it: Consumer Affairs Victoria (opens in a new tab) gives air conditioning as an example of a provisional sum, which is an estimate, not a fixed price. If you use your own installer, the builder has to know who is coming, when, and what the rough-in needs from the frame.

Can the pipes be roughed in now and the units fitted later?

Yes, and that is the usual way. The pipes and drains go in before the linings, and the units are fitted near the end, once the dusty work is done.

What if the plan changes after the walls are up?

Then the change means cutting and patching, and it may need a variation to the building contract. The guide to planning air conditioning through a renovation covers changes during building work.

Sources (19)

Building a new home?

Send your plans and checklist with an enquiry, or call ABL to talk through the rough-in.